6129 N GLIDE AVE 91367
Certificate Information: 6129 N GLIDE AVE 91367
- Application / Permit
- 20014-20000-00403
- Plan Check / Job No.
- B20VN01537
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- TWO STORY ADDITION AND REMODEL TO EXISTING SFD
- Permit Issued
- Issued on 12/10/2020
- Issuing Office
- Current Status
- CofO Issued on 1/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2020 | APPLICANT |
| Green Plans Picked Up | 3/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | ADAM HEGAZI |
| Corrections Issued | 3/10/2020 | ADAM HEGAZI |
| Quality Review Completed | 3/15/2020 | YOUNG KIM |
| Applicant returned to address corrections | 7/30/2020 | ADAM HEGAZI |
| Plan Check Approved | 11/6/2020 | ADAM HEGAZI |
| Issued | 12/10/2020 | APPLICANT |
| Building Plans Picked Up | 12/17/2020 | APPLICANT |
| CofO in Progress | 9/20/2022 | TROY SANDERS |
| Permit Finaled | 1/13/2023 | JOHN JANSON |
| CofO Issued | 1/13/2023 | JOHN JANSON |
| Permit Finaled | 1/13/2023 | JOHN JANSON |
Permit Application Clearance Information
| Green Code | Cleared | 6/30/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 9/23/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 10/15/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/14/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 12/13/2021 | Partial Approval | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 12/22/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 12/22/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/12/2022 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 4/8/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 4/8/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/27/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/11/2022 | Approved | TROY SANDERS |
| Green Building Rough | 5/11/2022 | Not Ready for Inspection | TROY SANDERS |
| Insulation | 6/3/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/3/2022 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 6/3/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/13/2022 | Approved | TROY SANDERS |
| Green Building Rough | 6/13/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 7/5/2022 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 9/19/2022 | Approved | TROY SANDERS |
| Final | 9/19/2022 | Partial Approval | TROY SANDERS |
| Gas Test | 9/19/2022 | Approved | TROY SANDERS |
| HVAC-Final | 9/19/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 9/19/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/19/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/19/2022 | Approved | TROY SANDERS |
| Final | 9/20/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 9/20/2022 | Approved | TROY SANDERS |