6129 N GLIDE AVE 91367

Certificate Information: 6129 N GLIDE AVE 91367

Application / Permit
20014-20000-00403
Plan Check / Job No.
B20VN01537
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
TWO STORY ADDITION AND REMODEL TO EXISTING SFD
Permit Issued
Issued on 12/10/2020
Issuing Office
Current Status
CofO Issued on 1/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/30/2020 APPLICANT
Green Plans Picked Up 3/3/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 ADAM HEGAZI
Corrections Issued 3/10/2020 ADAM HEGAZI
Quality Review Completed 3/15/2020 YOUNG KIM
Applicant returned to address corrections 7/30/2020 ADAM HEGAZI
Plan Check Approved 11/6/2020 ADAM HEGAZI
Issued 12/10/2020 APPLICANT
Building Plans Picked Up 12/17/2020 APPLICANT
CofO in Progress 9/20/2022 TROY SANDERS
Permit Finaled 1/13/2023 JOHN JANSON
CofO Issued 1/13/2023 JOHN JANSON
Permit Finaled 1/13/2023 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 6/30/2020 DAVID MATSON
Low Impact Development Cleared 9/23/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 10/15/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/2/2020 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/14/2021 Approved TROY SANDERS
PLUMBING-Rough 12/13/2021 Partial Approval TROY SANDERS
Excavation/Setback/Form/Re-Bar 12/22/2021 Approved TROY SANDERS
Footing/Foundation/Slab 12/22/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/12/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/14/2022 Partial Approval TROY SANDERS
ELECTRICAL-Rough 4/8/2022 Approved TROY SANDERS
HVAC-Rough 4/8/2022 Approved TROY SANDERS
PLUMBING-Rough 4/27/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 5/11/2022 Approved TROY SANDERS
Green Building Rough 5/11/2022 Not Ready for Inspection TROY SANDERS
Insulation 6/3/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/3/2022 Partial Approval VINCENT HANLEY
Shower Pan 6/3/2022 Approved VINCENT HANLEY
Drywall Nailing 6/13/2022 Approved TROY SANDERS
Green Building Rough 6/13/2022 Approved TROY SANDERS
Interior/Exterior Lathing 7/5/2022 Approved JESUS PINEDA
ELECTRICAL-Final 9/19/2022 Approved TROY SANDERS
Final 9/19/2022 Partial Approval TROY SANDERS
Gas Test 9/19/2022 Approved TROY SANDERS
HVAC-Final 9/19/2022 Approved TROY SANDERS
PLUMBING-Final 9/19/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 9/19/2022 Approved TROY SANDERS
Final 9/20/2022 OK to Issue CofO TROY SANDERS
Green Building Final 9/20/2022 Approved TROY SANDERS