1805-1805 1/2 E 105TH ST 90002

Certificate Information: 1805-1805 1/2 E 105TH ST 90002

Application / Permit
20014-20000-00394
Plan Check / Job No.
B20VN01509
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 8'-2" X 15'-2" ATTACHED GARAGE TO (N) BEDROOM FOR (E) SFD; ADD IRREGULAR 17'-0" X 50'-2" ACCESSORY DWELLING UNIT PER GCS 65852.2(E)(1)(A) AND 8'-6" X 18'-6" 1-CAR GARAGE. ALL WORK PER WFPP.
Permit Issued
Issued on 7/10/2020
Issuing Office
Current Status
CofO Issued on 3/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2020 APPLICANT
Green Plans Picked Up 2/12/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 JENNIFER LEE
Corrections Issued 2/25/2020 JENNIFER LEE
Quality Review Completed 2/25/2020 STEVEN KIM
Building Plans Picked Up 2/27/2020 APPLICANT
Plan Check Approved 7/8/2020 JENNIFER LEE
Issued 7/10/2020 APPLICANT
CofO in Progress 6/13/2022 JOHN KLARIN
Permit Finaled 3/25/2023 DANIEL ORRANTE
Permit Finaled 3/25/2023 DANIEL ORRANTE
CofO Issued 3/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/16/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 3/16/2020 THOMAS LANG
Permit Cleared 3/16/2020 THOMAS LANG
Sewer availability Cleared 3/16/2020 THOMAS LANG
Community Plan Implem. Overlay Cleared 3/17/2020 LAUREN PADICK
Green Code Cleared 3/17/2020 AARON COSTA
ZI Cleared 3/17/2020 LAUREN PADICK
Trees in Parkway Cleared 4/23/2020 JOHN KIM
Low Impact Development Cleared 6/17/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/26/2020 JEANIE LAM

Contact Information

Contractor Hanu Ilan Construction; Lic. No.: 468132-B 15227 CHASE ST #20      NORTH HILLS, CA 91363

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/20/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/28/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/13/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Partial Approval EUGENE CASSIDY
HVAC-Rough 8/13/2020 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 8/13/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/25/2020 Approved EUGENE CASSIDY
Green Building Rough 9/25/2020 Approved EUGENE CASSIDY
Insulation 9/25/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 9/25/2020 Partial Approval EUGENE CASSIDY
Drywall Nailing 10/2/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/2/2020 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 10/9/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 10/19/2020 Approved EUGENE CASSIDY
Footing/Foundation/Slab 10/19/2020 Approved EUGENE CASSIDY
Insulation 10/19/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 1/6/2021 Not Ready for Inspection EUGENE CASSIDY
Final 1/6/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 1/6/2021 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 1/6/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 1/6/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 1/6/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 1/6/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 1/13/2021 Approved EUGENE CASSIDY
Final 1/13/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 1/13/2021 Corrections Issued EUGENE CASSIDY
HVAC-Final 1/13/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Final 1/13/2021 Approved EUGENE CASSIDY
Smoke Detectors 1/13/2021 Approved EUGENE CASSIDY
Green Building Final 2/3/2021 Approved EUGENE CASSIDY
HVAC-Final 2/3/2021 Approved EUGENE CASSIDY
HVAC-Rough 2/3/2021 Approved EUGENE CASSIDY
Final 2/1/2022 Corrections Issued JOHN KLARIN
Final 2/7/2022 Not Ready for Inspection JOHN KLARIN
Pre-Inspection 2/10/2022 Corrections Issued JOHN KLARIN
Final 2/23/2022 Not Ready for Inspection JOHN KLARIN
Final 3/7/2022 No Access for Inspection JOHN KLARIN
Final 4/14/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Final 4/18/2022 Approved JOHN KLARIN
HVAC-Final 4/18/2022 Approved JOHN KLARIN
MERV13>=Final 4/18/2022 Approved JOHN KLARIN
PLUMBING-Final 4/18/2022 Approved JOHN KLARIN
Pre-Inspection 4/18/2022 Not Ready for Inspection JOHN KLARIN
Final 6/1/2022 Not Ready for Inspection JOHN KLARIN
Final 6/10/2022 Corrections Issued JOHN KLARIN
Final 6/13/2022 OK to Issue CofO JOHN KLARIN