13375 N AZORES AVE 91342
Certificate Information: 13375 N AZORES AVE 91342
- Application / Permit
- 20014-20000-00393
- Plan Check / Job No.
- B20VN01506
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 37'-6" X 12' ADDITION OF COVERED PATIO WITH DECK ABOVE
- Permit Issued
- Issued on 2/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | SELLA BENYAMIN |
| Corrections Issued | 1/31/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 2/3/2020 | APPLICANT |
| Plan Check Approved | 2/13/2020 | SELLA BENYAMIN |
| Issued | 2/20/2020 | LADBS |
| CofO in Progress | 6/9/2021 | MISAEL ESPARZA |
| Permit Finaled | 6/11/2021 | MICHAEL SMITH |
| CofO Issued | 6/11/2021 | MICHAEL SMITH |
| Permit Finaled | 6/11/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/12/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 2/12/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | 5 Stars Remodeling & Construction Inc; Lic. No.: 1041788-B | 7900 JAMIESON AVE RESEDA, CA 91335 |
| Engineer | Lao,, Arturo Begino; Lic. No.: C56687 | 16348 MIDWOOD DR GRANADA HILLS, CA 91344 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/4/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/4/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Wood Frame | 3/4/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 3/10/2020 | Approved | MICHEL ABAJAN |
| Wood Frame | 3/10/2020 | Approved | MICHEL ABAJAN |
| Special/Order Compliance | 3/12/2021 | Approved | RICHARD DOCKUS |
| Final | 6/8/2021 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 6/8/2021 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/8/2021 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 6/8/2021 | Approved | MISAEL ESPARZA |