4464 W COLLEGE VIEW AVE 90041

Certificate Information: 4464 W COLLEGE VIEW AVE 90041

Application / Permit
20014-20000-00389
Plan Check / Job No.
B20VN01495
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT (IRREGULAR SHAPE) PER GCS 65852.2(e)(1)(B).
Permit Issued
Issued on 10/18/2022
Issuing Office
Metro
Current Status
Issued on 10/18/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/29/2020 APPLICANT
Green Plans Picked Up 2/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 ALBERT SERVIN
Corrections Issued 3/10/2020 ALBERT SERVIN
Quality Review Completed 3/12/2020 KEN GILL
Building Plans Picked Up 4/3/2020 APPLICANT
Applicant returned to address corrections 5/13/2022 ALBERT SERVIN
Applicant returned to address corrections 6/29/2022 ALBERT SERVIN
Applicant returned to address corrections 10/7/2022 ALBERT SERVIN
Plan Check Approved 10/18/2022 ALBERT SERVIN
Issued 10/18/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/9/2020 ELAINE LEI
BHO/Hillside ordinance Cleared 6/9/2020 ELAINE LEI
BHO/Hillside ordinance Cleared 6/9/2020 ELAINE LEI
BHO/Hillside ordinance Cleared 6/9/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 6/9/2020 ELAINE LEI
Sewer availability Cleared 6/9/2020 ELAINE LEI
GPI Written Notices Cleared 7/21/2020 ALBERT SERVIN
Grading Pre-Inspection Cleared 7/21/2020 ALBERT SERVIN
Hydrant and Access approval Cleared 8/20/2020 MATTHEW CRAIG
Green Code Cleared 10/27/2020 DAVID MATSON
Low Impact Development Cleared 3/3/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/8/2022 AMAAN MALIK
Construction near power lines Cleared 10/17/2022 TORI CHEN

Contact Information

Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/23/2022 Corrections Issued AMY COLIN
Footing/Foundation/Slab 1/12/2023 Partial Approval CRAIG VAUGHAN
Pre-Inspection 6/14/2023 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 7/28/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 8/8/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 9/20/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 9/20/2023 Corrections Issued CRAIG VAUGHAN
Green Building Rough 9/20/2023 Approved CRAIG VAUGHAN
HVAC-Rough 9/20/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 9/20/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 9/29/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 9/29/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 9/29/2023 Partial Approval CRAIG VAUGHAN
Verify Sprinkler Sign Off 9/29/2023 Approved CRAIG VAUGHAN
Insulation 10/13/2023 Approved CRAIG VAUGHAN
Drywall Nailing 10/26/2023 Approved SCOTT FINNILA
HVAC-Rough 10/26/2023 Approved SCOTT FINNILA
Shower Pan 11/7/2023 Approved ROY SPAULDING
Interior/Exterior Lathing 11/16/2023 Approved CRAIG VAUGHAN
Gas Test 9/3/2024 Approved ROY SPAULDING
Underground Mechanical 9/3/2024 Partial Approval ROY SPAULDING
Service/Power Release 12/5/2024 Not Ready for Inspection ROY SPAULDING
Final 5/13/2026 Not Ready for Inspection RONNIE MEDINA
Green Building Final 5/13/2026 Not Ready for Inspection RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 5/13/2026 SGSOV Not Ready RONNIE MEDINA
Service/Power Release 5/13/2026 Not Ready for Inspection RONNIE MEDINA
Smoke Detectors 5/13/2026 Corrections Issued RONNIE MEDINA