5443 N ENCINO AVE 91316
Certificate Information: 5443 N ENCINO AVE 91316
- Application / Permit
- 20014-20000-00374
- Plan Check / Job No.
- B20VN01434
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION (1ST FLOOR OF 819.43 SQFT AND 2ND FLOOR OF 705.82 SQFT) AND REMODEL TO (E) 2-STORY SFD. 1 OF 3.
- Permit Issued
- Issued on 12/2/2020
- Issuing Office
- Current Status
- CofO Issued on 2/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | CHUNG-WEN CHUANG |
| Corrections Issued | 3/31/2020 | CHUNG-WEN CHUANG |
| Quality Review Completed | 4/28/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 5/4/2020 | APPLICANT |
| Green Plans Picked Up | 5/4/2020 | APPLICANT |
| Plan Check Approved | 10/29/2020 | CHUNG-WEN CHUANG |
| Issued | 12/2/2020 | APPLICANT |
| CofO in Progress | 2/2/2022 | VINCENT HANLEY |
| Permit Finaled | 2/17/2022 | RONALD MYRICK |
| CofO Issued | 2/17/2022 | RONALD MYRICK |
| Permit Finaled | 2/17/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/7/2020 | GABRIEL ROBLES |
| ZI | Cleared | 8/20/2020 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 9/9/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/14/2020 | SARAH YOUSSEF |
| Green Code | Cleared | 9/25/2020 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 9/30/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/13/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Footing/Foundation/Slab | 5/12/2021 | Partial Approval | STEVEN BACK |
| Deputy Reinf. Concrete | 5/13/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 5/13/2021 | Partial Approval | STEVEN BACK |
| Deputy Drilled-In Anchors | 5/20/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Partial Approval | RONALD COWAN |
| Deputy Drilled-In Anchors | 5/25/2021 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 6/2/2021 | Approved | STEVEN BACK |
| Underground Mechanical | 6/2/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 7/7/2021 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 7/7/2021 | Approved | STEVEN BACK |
| Insulation | 7/7/2021 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 7/7/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 7/7/2021 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/27/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 7/27/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 7/27/2021 | Approved | DAVID SANDOVAL |
| MERV13>=Rough | 7/27/2021 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 7/27/2021 | Approved | DAVID SANDOVAL |
| Insulation | 7/30/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/2/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 8/2/2021 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 8/9/2021 | Approved | RYAN SALAZAR |
| Pre-Inspection | 8/9/2021 | Partial Inspection | STEPHANIE SWANSON |
| Shower Pan | 8/9/2021 | Not Ready for Inspection | RYAN SALAZAR |
| Shower Pan | 8/19/2021 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 9/13/2021 | Approved | RYAN SALAZAR |
| Final | 12/22/2021 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/22/2021 | SGSOV Approved | SEAN HAUPT |
| Final | 1/27/2022 | Corrections Issued | PETER FOLLING |
| Green Building Final | 1/27/2022 | Not Ready for Inspection | PETER FOLLING |
| MERV13>=Final | 1/27/2022 | Approved | PETER FOLLING |
| Smoke Detectors | 1/27/2022 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 2/2/2022 | Approved | VINCENT HANLEY |
| Final | 2/2/2022 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 2/2/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 2/2/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/2/2022 | Approved | VINCENT HANLEY |