8516 N YOLANDA AVE 91324

Certificate Information: 8516 N YOLANDA AVE 91324

Application / Permit
20014-20000-00359
Plan Check / Job No.
B20VN01386
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRREGULAR 34'-1" X 41'-1" FOR (N) BEDROOMS/BATHROOMS TO AN (E) 1-STORY SFD PER ENGINEERING
Permit Issued
Issued on 3/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2020 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 JENNIFER LEE
Corrections Issued 1/30/2020 JENNIFER LEE
Plan Check Approved 3/17/2020 RAPHAEL ROSAS
Issued 3/17/2020 LADBS
CofO in Progress 3/15/2023 DAVID SCANTLIN
CofO in Progress 4/25/2023 DAVID SCANTLIN
CofO in Progress 4/25/2023 DAVID SCANTLIN
Permit Finaled 4/25/2023 JOHN JANSON
CofO Issued 4/25/2023 JOHN JANSON
Permit Finaled 4/25/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/30/2020 JOHN LIN
Sewer availability Cleared 1/30/2020 JOHN LIN
Low Impact Development Cleared 3/2/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/2/2020 THOMAS LANG
Construction near power lines Cleared 3/13/2020 RIDWAN HARDY

Contact Information

Contractor Sire Energy Construction; Lic. No.: 1027415-B 21054 SHERMAN WAY #325      CANOGA PARK, CA 91303
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/5/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 5/7/2020 Partial Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 5/12/2020 Corrections Issued HENRY KIM
Footing/Foundation/Slab 5/12/2020 Corrections Issued HENRY KIM
Excavation/Setback/Form/Re-Bar 6/9/2020 Approved DAVID SCANTLIN
Footing/Foundation/Slab 6/9/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 6/29/2020 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 6/29/2020 Not Ready for Inspection JEFFREY PARD
Green Building Rough 6/29/2020 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 6/29/2020 Not Ready for Inspection JEFFREY PARD
Wood Frame 6/29/2020 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 8/17/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 8/17/2020 Not Ready for Inspection JEFFREY PARD
Green Building Rough 8/17/2020 Approved JEFFREY PARD
PLUMBING-Rough 8/17/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 8/20/2020 Approved JEFFREY PARD
PLUMBING-Rough 8/20/2020 Approved JEFFREY PARD
Wood Frame 8/20/2020 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 9/11/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 9/11/2020 Approved JEFFREY PARD
Shower Pan 9/11/2020 Approved JEFFREY PARD
Underground Mechanical 9/11/2020 Not Ready for Inspection JEFFREY PARD
Insulation 9/15/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 9/15/2020 Approved JEFFREY PARD
Underground Mechanical 9/15/2020 Approved JEFFREY PARD
Drywall Nailing 9/21/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 10/13/2020 Approved DONALD SUNSERI
SGSOV-Seismic Gas S/O Valve 3/2/2021 SGSOV Not Ready JEFFREY PARD
Final 4/15/2021 Corrections Issued JEFFREY PARD
Green Building Final 4/15/2021 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 4/15/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 4/15/2021 Approved JEFFREY PARD
Final 8/11/2022 Corrections Issued JEFFREY PARD
Final 3/10/2023 No Access for Inspection DAVID SCANTLIN
Final 4/25/2023 OK to Issue CofO DAVID SCANTLIN