19138 W CALVERT ST 91335

Certificate Information: 19138 W CALVERT ST 91335

Application / Permit
20014-20000-00358
Plan Check / Job No.
B20VN01384
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16'-6" X 38'-9" IRREGULAR SHAPE ADDITION TO (E) SFD TO RELOCATE (E) KITCHEN, DINING/ LIVING ROOM, CLOSET AND NEW 1/2 BATHROOM. NEW 10'-0" X 38'-9" ATTACHED OPEN TRELLIS PATIO. ALL WORK PER ENGINEER DESIGN.
Permit Issued
Issued on 9/9/2020
Issuing Office
Current Status
CofO Issued on 7/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2020 APPLICANT
Assigned to Plan Check Engineer 1/28/2020 ALDOUS CHIC
Corrections Issued 1/28/2020 ALDOUS CHIC
Plan Check Approved 5/4/2020 ROSENDO MEDINA
Issued 9/9/2020 APPLICANT
CofO in Progress 7/6/2021 STEVEN BACK
Permit Finaled 7/7/2021 JOHN JANSON
CofO Issued 7/7/2021 JOHN JANSON
Permit Finaled 7/7/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2020 GABRIEL ROBLES
Sewer availability Cleared 1/28/2020 GABRIEL ROBLES
ZI Cleared 1/28/2020 STEVEN WECHSLER
Low Impact Development Cleared 4/14/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/21/2020 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C89103 1010 RALEIGH ST   APT 107    GLENDALE, CA 91205

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/24/2020 Approved STEVEN BACK
Footing/Foundation/Slab 9/24/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 10/2/2020 Partial Approval STEVEN BACK
PLUMBING-Rough 10/2/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/16/2020 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 10/21/2020 Approved STEVEN BACK
HVAC-Rough 10/21/2020 Approved STEVEN BACK
PLUMBING-Rough 10/21/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 10/22/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Approved STEVEN BACK
Insulation 10/29/2020 Approved STEVEN BACK
Interior/Exterior Lathing 10/29/2020 Partial Approval STEVEN BACK
Drywall Nailing 11/5/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 12/24/2020 Approved STEVEN BACK
Final 12/30/2020 No Access for Inspection PAUL CHOPP
SGSOV-Seismic Gas S/O Valve 12/30/2020 SGSOV Not Ready PAUL CHOPP
Smoke Detectors 12/30/2020 No Access for Inspection PAUL CHOPP
Final 2/22/2021 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Approved STEVEN BACK
Smoke Detectors 2/22/2021 Approved STEVEN BACK
ELECTRICAL-Final 6/16/2021 Not Ready for Inspection HENRY KIM
Final 6/16/2021 Not Ready for Inspection HENRY KIM
HVAC-Final 6/16/2021 Not Ready for Inspection HENRY KIM
PLUMBING-Final 6/16/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 7/6/2021 Approved STEVEN BACK
Final 7/6/2021 OK to Issue CofO STEVEN BACK
HVAC-Final 7/6/2021 Approved STEVEN BACK
PLUMBING-Final 7/6/2021 Approved STEVEN BACK