13429 W TIARA ST 91401
Certificate Information: 13429 W TIARA ST 91401
- Application / Permit
- 20014-20000-00351
- Plan Check / Job No.
- B20VN01353
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 45-6" X 37'-4" IRR.-SHAPED ADDITION AND INTERIOR REMODEL TO ADD (1) LAUNDRY, STUDY ROOM, (1) BATHROOM & REMODEL (1) BATHROOM/KITCHEN TO (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 1/28/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2020 | SARKIS HARABEDIAN |
| Corrections Issued | 1/28/2020 | SARKIS HARABEDIAN |
| Plan Check Approved | 1/28/2020 | GURUNATH NESARAJAH |
| Issued | 1/28/2020 | LADBS |
| CofO in Progress | 1/20/2023 | JOHN COLEMAN |
| CofO Issued | 4/18/2023 | MICHAEL SMITH |
| Permit Finaled | 4/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 1/28/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/28/2020 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2020 | Approved | GREG ALLTON |
| METHANE-Barrier | 2/10/2020 | Approved | GREG ALLTON |
| METHANE-Subgrade | 2/10/2020 | Approved | GREG ALLTON |
| PLUMBING-Rough | 2/10/2020 | Partial Approval | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2020 | Approved | GREG ALLTON |
| PLUMBING-Rough | 4/1/2020 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 4/2/2020 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 4/2/2020 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/8/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 4/8/2020 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 4/8/2020 | Approved | BRENDAN LOONEY |
| METHANE-Rough | 4/8/2020 | Approved | BRENDAN LOONEY |
| Shower Pan | 4/8/2020 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/14/2020 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 4/14/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 4/22/2020 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2020 | Approved | BRENDAN LOONEY |
| Green Building Rough | 4/22/2020 | Approved | BRENDAN LOONEY |
| Insulation | 4/29/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 5/5/2020 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 5/11/2020 | Approved | BRENDAN LOONEY |
| Shower Pan | 5/13/2020 | Approved | BRENDAN LOONEY |
| Special/Order Compliance | 5/22/2020 | Approved | ROBERT MINASSIANS |
| Green Building Final | 5/24/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/24/2021 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 5/24/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 11/10/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 4/20/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/20/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Final | 4/20/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Final | 4/20/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 7/6/2022 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Approved | RAFAEL CORTES |
| Final | 11/8/2022 | Corrections Issued | JOHN HAYES |
| Final | 1/19/2023 | OK to Issue CofO | JOHN COLEMAN |