3513 S MAPLEWOOD AVE 90066
Certificate Information: 3513 S MAPLEWOOD AVE 90066
- Application / Permit
- 20014-20000-00347
- Plan Check / Job No.
- B20VN01331
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING, ADD 29' 9" X 32' IRR.-SHAPE TO REAR, 5' 6" X 12' 7" TO FRONT AND 5' 6" X 21' 5" ENTRY PORCH. ALL WORK DONE PER STRUCTURAL ENGINEERING. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED.
- Permit Issued
- Issued on 7/8/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 2/23/2020 | GURUNATH NESARAJAH |
| Quality Review Completed | 2/25/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Green Plans Picked Up | 2/27/2020 | APPLICANT |
| Plan Check Approved | 6/22/2020 | GURUNATH NESARAJAH |
| Issued | 7/8/2020 | APPLICANT |
| CofO in Progress | 3/17/2021 | ENRIQUE MIRELES |
| CofO Issued | 4/6/2021 | VINCENT COTTON |
| Permit Finaled | 4/6/2021 | VINCENT COTTON |
Permit Application Clearance Information
| ZI | Cleared | 4/7/2020 | MIGUEL GAMBOA |
| Green Code | Cleared | 4/20/2020 | DAVID MATSON |
| Grading Pre-Inspection | Cleared | 4/23/2020 | KIRK LINKLATER |
| Low Impact Development | Cleared | 6/11/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/17/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/17/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | DINAH GARIN |
| GPI Written Notices | Cleared | 6/22/2020 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/28/2020 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 7/30/2020 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Sewer | 8/7/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/11/2020 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2020 | Partial Approval | DAVID HEINE |
| Deputy Wood Construction | 9/3/2020 | No Access for Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Approved | CRAIG DAVIS |
| HVAC-Rough | 9/16/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/16/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/21/2020 | Corrections Issued | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/23/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/23/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 9/23/2020 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 9/23/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/5/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 10/13/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/13/2020 | Approved | ENRIQUE MIRELES |
| Shower Pan | 10/14/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/16/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/19/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/16/2021 | Approved | ENRIQUE MIRELES |
| Final | 2/16/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 2/16/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 2/16/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 2/16/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/16/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/16/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 2/16/2021 | Approved | ENRIQUE MIRELES |
| Final | 2/18/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 3/17/2021 | OK to Issue CofO | ENRIQUE MIRELES |