512 W 52ND PL 90037

Certificate Information: 512 W 52ND PL 90037

Application / Permit
20014-20000-00332
Plan Check / Job No.
B20VN01274
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADDITION TO & CONVERT (E) DET. GARAGE TO ADU AND ATTACHED STORAGE .COMPLY WITH DEPARTMENT ORDER effective date 01/10/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 3/12/2021
Issuing Office
Metro
Current Status
CofO Issued on 2/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 ARSALAN SHABESTARI
Corrections Issued 3/9/2020 ARSALAN SHABESTARI
Quality Review Completed 3/26/2020 HERNAN ARREOLA
Building Plans Picked Up 3/27/2020 APPLICANT
Applicant returned to address corrections 10/6/2020 ARSALAN SHABESTARI
Green Plans Picked Up 11/6/2020 APPLICANT
Plan Check Approved 1/20/2021 ARSALAN SHABESTARI
Issued 3/12/2021 APPLICANT
CofO in Progress 12/17/2024 DANIEL GONZALEZ
Permit Finaled 2/24/2025 CLAUDIO MORENO
CofO Issued 2/24/2025 CLAUDIO MORENO
Permit Finaled 2/24/2025 CLAUDIO MORENO

Permit Application Clearance Information

Construction near power lines Cleared 9/1/2020 RIDWAN HARDY
Construction within easement Cleared 9/1/2020 RIDWAN HARDY
Address approval Cleared 9/10/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 9/10/2020 RENZ SORIANO
Sewer availability Cleared 9/14/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/15/2020 RENZ SORIANO
CPC Cleared 9/18/2020 SARAHI ORTEGA
Community Plan Implem. Overlay Cleared 9/18/2020 SARAHI ORTEGA
Green Code Cleared 11/6/2020 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEREMY TODD, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
MARVIN FONSECA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GUEVARA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/24/2021 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 5/10/2021 Partial Inspection MEL KHACHATOURIAN
Footing/Foundation/Slab 5/10/2021 Partial Inspection MEL KHACHATOURIAN
Pre-Inspection 8/10/2021 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 11/13/2024 Approved DANIEL GONZALEZ
Final 11/13/2024 Corrections Issued DANIEL GONZALEZ
Footing/Foundation/Slab 11/13/2024 Approved DANIEL GONZALEZ
Green Building Final 11/13/2024 Not Ready for Inspection DANIEL GONZALEZ
Green Building Rough 11/13/2024 Approved DANIEL GONZALEZ
MERV13>=Final 11/13/2024 Not Ready for Inspection DANIEL GONZALEZ
MERV13>=Rough 11/13/2024 Approved DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 11/13/2024 SGSOV Not Ready DANIEL GONZALEZ
Smoke Detectors 11/13/2024 Approved DANIEL GONZALEZ
Final 12/3/2024 Not Ready for Inspection DANIEL GONZALEZ
Green Building Final 12/3/2024 Not Ready for Inspection DANIEL GONZALEZ
MERV13>=Final 12/3/2024 Not Ready for Inspection DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Not Ready DANIEL GONZALEZ
Final 12/16/2024 OK to Issue CofO DANIEL GONZALEZ
Green Building Final 12/16/2024 Approved DANIEL GONZALEZ
MERV13>=Final 12/16/2024 Approved DANIEL GONZALEZ
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved DANIEL GONZALEZ
Service/Power Release 12/16/2024 Approved DANIEL GONZALEZ