13966 W VAN NUYS BLVD 91331

Certificate Information: 13966 W VAN NUYS BLVD 91331

Application / Permit
20014-20000-00331
Plan Check / Job No.
B20VN01267
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT RECREATION ROOM TO ADU WITH ADDITION. COMPLY WITH DEPARTMENT ORDER effective date11/28/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 10/17/2021
Issuing Office
Current Status
Issued on 10/17/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/27/2020 APPLICANT
Green Plans Picked Up 2/28/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 CRYSTEL MAALOUF
Corrections Issued 3/17/2020 CRYSTEL MAALOUF
Quality Review Completed 3/26/2020 BILL STUTSMAN
Plan Check Approved 10/7/2021 CRYSTEL MAALOUF
Issued 10/17/2021 APPLICANT
Building Plans Picked Up 10/25/2021 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 6/7/2020 RIDWAN HARDY
Green Code Cleared 7/27/2020 AARON COSTA
Address approval Cleared 8/6/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/10/2020 ADRIAN CASTRO
Sewer availability Cleared 8/10/2020 ADRIAN CASTRO
Low Impact Development Cleared 7/12/2021 MARTIN FRAGOSO
Stormwater Pollution Mitigatn Cleared 7/12/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/30/2021 ABDULLAH SADOZAI
Green Code Cleared 10/7/2021 CRYSTEL MAALOUF

Contact Information

Contractor Owner-Builder       ,
Engineer Chamberlain,, Robert Douglas; Lic. No.: C67937 7235 DE CELIS PL      VAN NUYS, CA 91406

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/5/2022 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 1/5/2022 Corrections Issued MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 1/5/2022 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 1/13/2022 Conditional Approval MICKEY YAMASHITA
ELECTRICAL-Final 1/13/2022 Corrections Issued MICKEY YAMASHITA
ELECTRICAL-Rough 1/13/2022 Conditional Approval MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Approved MICKEY YAMASHITA
Footing/Foundation/Slab 1/13/2022 Conditional Approval MICKEY YAMASHITA
Gas Test 1/13/2022 Approved MICKEY YAMASHITA
Green Building Final 1/13/2022 Approved MICKEY YAMASHITA
Green Building Rough 1/13/2022 Approved MICKEY YAMASHITA
HVAC-Final 1/13/2022 Approved MICKEY YAMASHITA
HVAC-Rough 1/13/2022 Approved MICKEY YAMASHITA
Insulation 1/13/2022 Approved MICKEY YAMASHITA
PLUMBING-Final 1/13/2022 Approved MICKEY YAMASHITA
PLUMBING-Rough 1/13/2022 Approved MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 1/13/2022 SGSOV Approved MICKEY YAMASHITA
Smoke Detectors 1/13/2022 Approved MICKEY YAMASHITA
BUILDING-Rough-Frame 1/19/2022 Approved MICKEY YAMASHITA
Final 1/19/2022 Partial Approval MICKEY YAMASHITA
Footing/Foundation/Slab 1/19/2022 Approved MICKEY YAMASHITA
MERV13>=Final 1/19/2022 Approved MICKEY YAMASHITA
MERV13>=Rough 1/19/2022 Approved MICKEY YAMASHITA
METHANE-Barrier 1/19/2022 Approved MICKEY YAMASHITA
METHANE-Final 1/19/2022 Approved MICKEY YAMASHITA
METHANE-Rough 1/19/2022 Approved MICKEY YAMASHITA
METHANE-Subgrade 1/19/2022 Approved MICKEY YAMASHITA