6040 W 74TH ST 90045

Certificate Information: 6040 W 74TH ST 90045

Application / Permit
20014-20000-00323
Plan Check / Job No.
B20VN01237
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) GARAGE AND CONVERSION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 5/10/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Green Plans Picked Up 2/26/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 LAMAR DAVIS
Corrections Issued 3/9/2020 LAMAR DAVIS
Quality Review Completed 3/20/2020 HERNAN ARREOLA
Building Plans Picked Up 5/27/2020 APPLICANT
Applicant returned to address corrections 2/24/2022 LAMAR DAVIS
Plan Check Approved 4/7/2022 LAMAR DAVIS
Issued 5/10/2022 APPLICANT
CofO in Progress 1/27/2023 BOBBY KEY
Permit Finaled 2/6/2023 DANIEL ORRANTE
CofO Issued 2/6/2023 DANIEL ORRANTE
Permit Finaled 2/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 1/15/2022 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 1/25/2022 JOSE HERNANDEZ
Sewer availability Cleared 1/25/2022 JOSE HERNANDEZ
Low Impact Development Cleared 2/25/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 3/9/2022 JENSON LEE
Construction near power lines Cleared 3/11/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 3/21/2022 VASIL MIHALEV
GPI Written Notices Cleared 3/24/2022 LAMAR DAVIS
Green Code Cleared 4/9/2022 LAMAR DAVIS

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/10/2022 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 6/14/2022 Approved BOBBY KEY
Underground Mechanical 6/14/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 8/3/2022 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 8/3/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 8/3/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Partial Approval BOBBY KEY
Gas Test 8/3/2022 Partial Approval BOBBY KEY
Green Building Rough 8/3/2022 Corrections Issued BOBBY KEY
HVAC-Rough 8/3/2022 Approved BOBBY KEY
PLUMBING-Rough 8/3/2022 Approved BOBBY KEY
Sewer 8/3/2022 Corrections Issued BOBBY KEY
Underground Mechanical 8/3/2022 Partial Approval BOBBY KEY
Green Building Rough 8/5/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 8/9/2022 Partial Approval BOBBY KEY
Green Building Rough 8/9/2022 Approved BOBBY KEY
Interior/Exterior Lathing 8/9/2022 Partial Approval BOBBY KEY
Insulation 8/12/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 8/15/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Approved BOBBY KEY
Drywall Nailing 8/18/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 8/19/2022 Partial Approval CLAYTON GRAHAM
Shower Pan 8/19/2022 Approved CLAYTON GRAHAM
ELECTRICAL-Final 1/20/2023 Approved BOBBY KEY
Final 1/20/2023 Corrections Issued BOBBY KEY
Green Building Final 1/20/2023 Approved BOBBY KEY
HVAC-Final 1/20/2023 Approved BOBBY KEY
PLUMBING-Final 1/20/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 1/20/2023 Approved BOBBY KEY
Final 1/27/2023 OK to Issue CofO BOBBY KEY