6038 W 74TH ST 90045

Certificate Information: 6038 W 74TH ST 90045

Application / Permit
20014-20000-00320
Plan Check / Job No.
B20VN01222
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 17'-7"x23' TO THE (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 2/7/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Assigned to Plan Check Engineer 1/24/2020 SEAN SHAHMIRI
Corrections Issued 1/24/2020 SEAN SHAHMIRI
Plan Check Approved 2/7/2020 KEVIN MORALES
Issued 2/7/2020 LADBS
CofO in Progress 1/23/2023 BOBBY KEY
Permit Finaled 1/23/2023 DANIEL ORRANTE
CofO Issued 1/23/2023 DANIEL ORRANTE
Permit Finaled 1/23/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/24/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 1/24/2020 BARTON HOLMES
Sewer availability Cleared 1/24/2020 ADRIAN CASTRO
Low Impact Development Cleared 2/7/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/7/2020 THOMAS LANG

Contact Information

Contractor G S E Construction; Lic. No.: 315558-B 18334 BLACKHAWK STREET      NORTHRIDGE, CA 91326
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/14/2020 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/20/2020 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/5/2020 Partial Inspection KENNETH NAGLE
Green Building Rough 3/5/2020 Not Ready for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Partial Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 4/16/2020 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 4/29/2020 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 4/29/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 4/29/2020 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 5/4/2020 Approved JUAN VALENZUELA
Insulation 5/4/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 5/4/2020 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 5/4/2020 Approved JUAN VALENZUELA
Shower Pan 5/4/2020 Approved JUAN VALENZUELA
Drywall Nailing 5/11/2020 Approved ANTHONY MCDOWALL
BUILDING-Rough-Frame 6/30/2020 Approved JUAN VALENZUELA
Final 6/30/2020 Corrections Issued JUAN VALENZUELA
Green Building Final 6/30/2020 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 6/30/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/30/2020 SGSOV Approved JUAN VALENZUELA
Smoke Detectors 6/30/2020 Approved JUAN VALENZUELA
Final 1/20/2023 OK to Issue CofO BOBBY KEY
Green Building Final 1/20/2023 Approved BOBBY KEY