10333 N KEOKUK AVE 91311

Certificate Information: 10333 N KEOKUK AVE 91311

Application / Permit
20014-20000-00300
Plan Check / Job No.
B20VN01133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
31' 8" X 34' 10" IRR.-SHAPE ADDITION & 20' 2" X 20' 1" IRR.-SHAPE PATIO COVER ADDITION TO FRONT OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 4/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Assigned to Plan Check Engineer 1/24/2020 GURUNATH NESARAJAH
Corrections Issued 1/24/2020 GURUNATH NESARAJAH
Building Plans Picked Up 1/27/2020 APPLICANT
Plan Check Approved 3/25/2020 GURUNATH NESARAJAH
Issued 4/3/2020 LADBS
CofO in Progress 4/4/2022 DAVID SCANTLIN
Permit Finaled 4/19/2022 JOHN JANSON
CofO Issued 4/19/2022 JOHN JANSON
Permit Finaled 4/19/2022 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/13/2020 BARTON HOLMES
Eng Process Fee Ord 176,300 Cleared 2/27/2020 GUILLERMO PETRA
Low Impact Development Cleared 2/27/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/27/2020 GUILLERMO PETRA
Sewer availability Cleared 2/27/2020 GUILLERMO PETRA
ZI Cleared 3/12/2020 STEVEN WECHSLER
GPI Written Notices Cleared 3/25/2020 GURUNATH NESARAJAH

Contact Information

Architect Woodcraft,, Lawrence Albert; Lic. No.: C23651 20812 VENTURA BLVD, STE 205      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/3/2020 Approved JEFFREY PARD
Deputy Drilled-In Anchors 9/11/2020 Approved JEFFREY PARD
PLUMBING-Rough 9/16/2020 Partial Approval JEFFREY PARD
PLUMBING-Rough 9/18/2020 Not Ready for Inspection JEFFREY PARD
Footing/Foundation/Slab 9/21/2020 Approved JEFFREY PARD
PLUMBING-Rough 9/21/2020 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 11/19/2020 Approved JEFFREY PARD
Green Building Rough 11/19/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 12/4/2020 Corrections Issued JEFFREY PARD
ELECTRICAL-Rough 12/4/2020 Approved JEFFREY PARD
Green Building Rough 12/4/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 12/4/2020 Approved JEFFREY PARD
PLUMBING-Rough 12/4/2020 Not Ready for Inspection JEFFREY PARD
BUILDING-Rough-Frame 12/14/2020 Approved JEFFREY PARD
Green Building Rough 12/14/2020 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 12/14/2020 Approved JEFFREY PARD
Rough-Elec/Plmb/HVAC 12/14/2020 Approved JEFFREY PARD
Insulation 12/21/2020 Approved JEFFREY PARD
Drywall Nailing 12/28/2020 Approved SEAN WIRCH
Shower Pan 1/19/2021 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/3/2022 Approved JEFFREY PARD
Final 3/3/2022 Corrections Issued JEFFREY PARD
Green Building Final 3/3/2022 Approved JEFFREY PARD
Green Building Rough 3/3/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 3/3/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 3/3/2022 Approved JEFFREY PARD
Final 4/1/2022 OK to Issue CofO DAVID SCANTLIN