3771 S ROSEWOOD AVE 90066

Certificate Information: 3771 S ROSEWOOD AVE 90066

Application / Permit
20014-20000-00295
Plan Check / Job No.
B20VN01117
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE AND ADD 8'-5"X 8'-7" ADDITION FOR NEW ACCESSORY DWELLNG UNIT
Permit Issued
Issued on 12/14/2020
Issuing Office
Current Status
CofO Issued on 11/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Green Plans Picked Up 2/20/2020 APPLICANT
Assigned to Plan Check Engineer 2/28/2020 ALYSSA N NARCISO
Corrections Issued 3/4/2020 ALYSSA N NARCISO
Quality Review Completed 3/11/2020 CHON CHIO KUO
Building Plans Picked Up 3/12/2020 APPLICANT
Applicant returned to address corrections 5/7/2020 ALYSSA N NARCISO
Plan Check Approved 5/15/2020 ALYSSA N NARCISO
Issued 12/14/2020 APPLICANT
CofO in Progress 11/16/2021 BOBBY KEY
Permit Finaled 11/22/2021 DANIEL ORRANTE
CofO Issued 11/22/2021 DANIEL ORRANTE
Permit Finaled 11/22/2021 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/31/2020 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 4/2/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 4/8/2020 ANTHONY MAINEZ
Sewer availability Cleared 4/8/2020 ANTHONY MAINEZ
Green Code Cleared 4/10/2020 AARON COSTA
Specific Plan Cleared 4/20/2020 FREDDY GARCIA
Hydrant and Access approval Cleared 4/28/2020 KURT CORRAL
Grading Pre-Inspection Cleared 5/7/2020 ALYSSA N NARCISO

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Carter Design & Remodeling Inc; Lic. No.: 932102-B 23890 COPPERHILL DRIVE #375      VALENCIA, CA 91354

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/2/2021 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 2/3/2021 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 2/8/2021 Approved ENRIQUE MIRELES
Deputy Drilled-In Anchors 2/25/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/8/2021 Approved ENRIQUE MIRELES
Gas Test 3/22/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 4/16/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 4/16/2021 Approved ENRIQUE MIRELES
Green Building Rough 4/16/2021 Approved ENRIQUE MIRELES
HVAC-Rough 4/16/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 4/16/2021 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 6/8/2021 Approved ENRIQUE MIRELES
Drywall Nailing 6/28/2021 Conditional Approval AMY COLIN
Interior/Exterior Lathing 6/28/2021 Approved AMY COLIN
Shower Pan 6/30/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 7/9/2021 Approved ENRIQUE MIRELES
Service/Power Release 9/23/2021 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/15/2021 SGSOV Not Ready ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Not Ready ENRIQUE MIRELES
Final 11/8/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 11/8/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 11/8/2021 SGSOV Gas Company BRENDAN LOONEY
Smoke Detectors 11/8/2021 Not Ready for Inspection BRENDAN LOONEY
Final 11/16/2021 OK to Issue CofO BOBBY KEY
Green Building Final 11/16/2021 Approved BOBBY KEY
Smoke Detectors 11/16/2021 Approved BOBBY KEY