4907 N VALJEAN AVE 91436

Certificate Information: 4907 N VALJEAN AVE 91436

Application / Permit
20014-20000-00293
Plan Check / Job No.
B20VN01109
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMO ENTIRE SFD W/ ATTACHED GARAGE EXCEPT FOR 1SF OF FOOTING & ADD 2-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 3/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 NILOOFAR MEHRAIN
Green Plans Picked Up 2/13/2020 APPLICANT
Corrections Issued 2/18/2020 NILOOFAR MEHRAIN
Quality Review Completed 2/18/2020 GUANG MIN TUNG
Building Plans Picked Up 2/19/2020 APPLICANT
Plan Check Approved 3/11/2020 NILOOFAR MEHRAIN
Issued 3/13/2020 LADBS
CofO in Progress 2/16/2021 RONALD COWAN
Permit Finaled 2/19/2021 DONALD SUNSERI
CofO Issued 2/19/2021 DONALD SUNSERI
Permit Finaled 2/19/2021 DONALD SUNSERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/19/2020 JOHN TRIANTAFYLLOS
Permit Cleared 2/19/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/19/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 2/21/2020 GEORGE SUCHAND
Green Code Cleared 2/25/2020 AARON COSTA
Trees in Parkway Cleared 2/26/2020 JOHN KIM
Low Impact Development Cleared 3/3/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 3/4/2020 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Askarian,, Soroosh Namaghi; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/17/2020 Approved RONALD COWAN
Excavation/Setback/Form/Re-Bar 4/23/2020 Approved RONALD COWAN
Footing/Foundation/Slab 4/23/2020 Approved RONALD COWAN
Interior/Exterior Lathing 6/8/2020 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 6/15/2020 Approved RONALD COWAN
HVAC-Rough 6/15/2020 Approved RONALD COWAN
Interior/Exterior Lathing 6/15/2020 Approved RONALD COWAN
PLUMBING-Rough 6/15/2020 Approved RONALD COWAN
Shower Pan 6/15/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 6/19/2020 Not Ready for Inspection RONALD COWAN
Green Building Rough 6/19/2020 Approved RONALD COWAN
BUILDING-Rough-Frame 6/22/2020 Approved RONALD COWAN
Insulation 6/22/2020 Approved RONALD COWAN
Drywall Nailing 6/26/2020 Approved RONALD COWAN
Green Building Final 1/8/2021 Approved RONALD COWAN
Service/Power Release 1/8/2021 Approved RONALD COWAN
Smoke Detectors 1/8/2021 Approved RONALD COWAN
Final 2/2/2021 Not Ready for Inspection RONALD COWAN
SGSOV-Seismic Gas S/O Valve 2/2/2021 SGSOV Approved RONALD COWAN
Final 2/11/2021 OK to Issue CofO RONALD COWAN