3039 S POTOMAC AVE 90016

Certificate Information: 3039 S POTOMAC AVE 90016

Application / Permit
20014-20000-00282
Plan Check / Job No.
B20VN01051
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO REMOVE ALL INTERIOR WALLS AND EXTERIOR WALLS ON SOUTH SIDE WITH LESS THAN 50% OF ROOF AREA TO BE REMOVED. ADD 52'10"X17'10" IRREGULAR SHAPED ADDITION & 15'11"X11'3" ADDITION TO (E) SFD.
Permit Issued
Issued on 9/1/2020
Issuing Office
Current Status
CofO Issued on 9/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2020 APPLICANT
Green Plans Picked Up 2/20/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 MARVEL DELACRUZ
Corrections Issued 3/11/2020 MARVEL DELACRUZ
Quality Review Completed 3/13/2020 GUANG MIN TUNG
Building Plans Picked Up 3/13/2020 APPLICANT
Applicant returned to address corrections 7/28/2020 MARVEL DELACRUZ
Applicant returned to address corrections 7/30/2020 MARVEL DELACRUZ
Plan Check Approved 8/19/2020 MARVEL DELACRUZ
Issued 9/1/2020 APPLICANT
CofO in Progress 10/19/2021 STUART CHAPMAN
Permit Finaled 9/30/2022 DEROLD HAUFF
CofO Issued 9/30/2022 DEROLD HAUFF
Permit Finaled 9/30/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 3/25/2020 AARON COSTA
Eng Process Fee Ord 176,300 Cleared 4/1/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 4/1/2020 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 4/17/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 6/16/2020 EMIL KYUPELYAN
Flood clearance Cleared 6/18/2020 RAYMOND LAM
Low Impact Development Cleared 7/14/2020 ROBIN YAMADA

Contact Information

Contractor Builders & Son'S Inc; Lic. No.: 961171-B 8720 VENICE BLVD STE 208      LOS ANGELES, CA 90034
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 9/22/2020 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 9/22/2020 Conditional Approval STUART CHAPMAN
ELECTRICAL-Rough 2/8/2021 Approved STUART CHAPMAN
Final 2/8/2021 Corrections Issued STUART CHAPMAN
HVAC-Rough 2/8/2021 Conditional Approval STUART CHAPMAN
PLUMBING-Rough 2/8/2021 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 2/10/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 2/10/2021 Approved STUART CHAPMAN
FLOOD-Proofing Certificate 2/10/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 2/10/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 2/10/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 2/10/2021 Conditional Approval STUART CHAPMAN
Pre-Inspection 2/10/2021 Approved STUART CHAPMAN
Wood Frame 2/10/2021 Approved STUART CHAPMAN
Insulation 3/3/2021 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 3/3/2021 Partial Approval STUART CHAPMAN
Shower Pan 3/3/2021 Approved STUART CHAPMAN
Drywall Nailing 3/10/2021 Partial Approval STUART CHAPMAN
Green Building Rough 3/10/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 3/10/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/14/2021 SGSOV Not Ready STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/28/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Final 6/29/2021 Corrections Issued KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Drywall Nailing 7/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
FLOOD-Elevation Certificate 7/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
FLOOD-Proofing Certificate 7/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 7/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 7/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 7/6/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 7/6/2021 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 7/6/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/2/2021 Approved RUBEN SALAS
Drywall Nailing 8/2/2021 Approved RUBEN SALAS
FLOOD-Elevation Certificate 8/2/2021 Approved RUBEN SALAS
FLOOD-Proofing Certificate 8/2/2021 Approved RUBEN SALAS
Final 8/2/2021 Conditional Approval RUBEN SALAS
Footing/Foundation/Slab 8/2/2021 Approved RUBEN SALAS
Green Building Final 8/2/2021 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 8/2/2021 SGSOV Approved RUBEN SALAS
Final 8/12/2021 Corrections Issued RUBEN SALAS
ELECTRICAL-Final 10/19/2021 Approved STUART CHAPMAN
Final 10/19/2021 OK to Issue CofO STUART CHAPMAN
HVAC-Final 10/19/2021 Approved STUART CHAPMAN
PLUMBING-Final 10/19/2021 Approved STUART CHAPMAN
Service/Power Release 10/19/2021 Approved STUART CHAPMAN