1603 W HILL DR 90041
Certificate Information: 1603 W HILL DR 90041
- Application / Permit
- 20014-20000-00269
- Plan Check / Job No.
- B20VN01022
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'-1" X 14'-6" ADDITION TO & CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 5/5/2021
- Issuing Office
- Current Status
- CofO Issued on 4/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 3/7/2020 | ARTIN ZARUKIAN |
| Quality Review Completed | 3/11/2020 | GUANG MIN TUNG |
| Green Plans Picked Up | 3/12/2020 | APPLICANT |
| Applicant returned to address corrections | 2/22/2021 | ARTIN ZARUKIAN |
| Plan Check Approved | 5/5/2021 | ARTIN ZARUKIAN |
| Issued | 5/5/2021 | APPLICANT |
| Building Plans Picked Up | 5/6/2021 | APPLICANT |
| CofO in Progress | 11/22/2021 | CRAIG VAUGHAN |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
| CofO Issued | 4/13/2022 | DEROLD HAUFF |
| Permit Finaled | 4/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2020 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 12/10/2020 | BRIAN MILLER |
| Roof/Waste drainage to street | Cleared | 1/19/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 1/19/2021 | RENZ SORIANO |
| Green Code | Cleared | 3/24/2021 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zolfaghari,, Saeed; Lic. No.: C86761 | 6201 BEE AVE AGOURA HILLS, CA 91301 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/25/2021 | Partial Approval | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 6/28/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/28/2021 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2021 | No Access for Inspection | SCOTT FINNILA |
| Underground Mechanical | 7/9/2021 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 7/13/2021 | Not Ready for Inspection | COREY HUPP |
| Underground Mechanical | 7/13/2021 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 7/22/2021 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 7/22/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/9/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/9/2021 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 9/9/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 9/9/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/9/2021 | Partial Approval | CRAIG VAUGHAN |
| Smoke Detectors | 9/9/2021 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/13/2021 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 9/13/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 9/20/2021 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 9/20/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 9/22/2021 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 9/29/2021 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 9/29/2021 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 10/1/2021 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 10/1/2021 | Approved | CHARLES BOGHOSKHAN |
| Final | 11/19/2021 | OK to Issue CofO | CRAIG VAUGHAN |
| Green Building Final | 11/19/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/19/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 11/19/2021 | Approved | CRAIG VAUGHAN |