1603 W HILL DR 90041

Certificate Information: 1603 W HILL DR 90041

Application / Permit
20014-20000-00269
Plan Check / Job No.
B20VN01022
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
15'-1" X 14'-6" ADDITION TO & CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 5/5/2021
Issuing Office
Current Status
CofO Issued on 4/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 ARTIN ZARUKIAN
Corrections Issued 3/7/2020 ARTIN ZARUKIAN
Quality Review Completed 3/11/2020 GUANG MIN TUNG
Green Plans Picked Up 3/12/2020 APPLICANT
Applicant returned to address corrections 2/22/2021 ARTIN ZARUKIAN
Plan Check Approved 5/5/2021 ARTIN ZARUKIAN
Issued 5/5/2021 APPLICANT
Building Plans Picked Up 5/6/2021 APPLICANT
CofO in Progress 11/22/2021 CRAIG VAUGHAN
Permit Finaled 4/13/2022 DEROLD HAUFF
CofO Issued 4/13/2022 DEROLD HAUFF
Permit Finaled 4/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/9/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 12/9/2020 RENZ SORIANO
Grading Pre-Inspection Cleared 12/10/2020 BRIAN MILLER
Roof/Waste drainage to street Cleared 1/19/2021 RENZ SORIANO
Sewer availability Cleared 1/19/2021 RENZ SORIANO
Green Code Cleared 3/24/2021 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/25/2021 Partial Approval BRIAN SULLIVAN
Deputy Drilled-In Anchors 6/28/2021 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 6/28/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 No Access for Inspection SCOTT FINNILA
Underground Mechanical 7/9/2021 Partial Approval COREY HUPP
PLUMBING-Rough 7/13/2021 Not Ready for Inspection COREY HUPP
Underground Mechanical 7/13/2021 Partial Approval COREY HUPP
BUILDING-Rough-Frame 7/22/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 7/22/2021 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 9/9/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 9/9/2021 Partial Approval CRAIG VAUGHAN
Green Building Rough 9/9/2021 Approved CRAIG VAUGHAN
HVAC-Rough 9/9/2021 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 9/9/2021 Partial Approval CRAIG VAUGHAN
Smoke Detectors 9/9/2021 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 9/13/2021 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 9/13/2021 Approved CRAIG VAUGHAN
Insulation 9/20/2021 Approved HAMIK HARTOUNIAN
Shower Pan 9/20/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/22/2021 Partial Approval CRAIG VAUGHAN
Drywall Nailing 9/29/2021 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 9/29/2021 Approved CHARLES BOGHOSKHAN
Drywall Nailing 10/1/2021 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 10/1/2021 Approved CHARLES BOGHOSKHAN
Final 11/19/2021 OK to Issue CofO CRAIG VAUGHAN
Green Building Final 11/19/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 11/19/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 11/19/2021 Approved CRAIG VAUGHAN