5229 N TEESDALE AVE 91607

Certificate Information: 5229 N TEESDALE AVE 91607

Application / Permit
20014-20000-00268
Plan Check / Job No.
B20VN01009
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
31'-3" X 29'-3" IRREG SHAPED ADDITION, 7'-5" X 7'-10" ADDITION, AND REMODEL TO (E) SINGLE FAMILY DWELLING TO ENLARGE KITCHEN AND FAMILY ROOM. RELOCATE LAUNDRY ROOM AND ADD ONE BEDROOM AND THREE BATHROOMS.
Permit Issued
Issued on 6/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/22/2020 APPLICANT
Green Plans Picked Up 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 JEROME MAGAT PALMA
Corrections Issued 2/18/2020 JEROME MAGAT PALMA
Quality Review Completed 2/18/2020 ABDUL CHEGENI
Building Plans Picked Up 2/19/2020 APPLICANT
Plan Check Approved 6/10/2020 JEROME MAGAT PALMA
Issued 6/22/2020 LADBS
CofO in Progress 8/20/2021 CHRISTOPHE COCHRAN
CofO Issued 9/11/2021 MICHAEL SMITH
Permit Finaled 9/11/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/12/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 3/12/2020 MARKOS PEREZ-BRAN
Low Impact Development Cleared 4/1/2020 ORVAL HERNANDEZ-MARCIAL
Green Code Cleared 6/3/2020 AARON COSTA
Roof/Waste drainage to street Cleared 6/4/2020 JOHN TRIANTAFYLLOS
Specific Plan Cleared 6/4/2020 MARIANNE KING
ZI Cleared 6/4/2020 MARIANNE KING

Contact Information

Contractor Owner-Builder       ,
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 2828 COCHRAN STREET 321      SIMI VALLEY, CA 93065

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2020 Approved BRENDAN LOONEY
Deputy Drilled-In Anchors 8/3/2020 Conditional Approval DANIEL ORRANTE
Insulation 8/3/2020 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 8/3/2020 Partial Approval BRENDAN LOONEY
Wood Frame 8/3/2020 Corrections Issued BRENDAN LOONEY
Wood Frame 8/4/2020 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Corrections Issued BRENDAN LOONEY
Deputy Wood Construction 10/30/2020 Conditional Approval DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 1/27/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 1/27/2021 Approved BRENDAN LOONEY
Green Building Rough 1/27/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 1/27/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 1/27/2021 Conditional Approval BRENDAN LOONEY
Wood Frame 1/27/2021 Conditional Approval BRENDAN LOONEY
Insulation 2/17/2021 Approved BRENDAN LOONEY
Shower Pan 2/17/2021 Approved BRENDAN LOONEY
Drywall Nailing 3/2/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 3/2/2021 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 3/9/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 7/8/2021 Approved ARAM AVEDISIAN
Final 7/8/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 7/8/2021 Approved ARAM AVEDISIAN
Green Building Rough 7/8/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/8/2021 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 7/8/2021 Approved ARAM AVEDISIAN
Final 8/11/2021 Conditional Approval CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 8/11/2021 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 8/11/2021 Not Ready for Inspection CHRISTOPHE COCHRAN