14435 W SAYRE ST 91342
Certificate Information: 14435 W SAYRE ST 91342
- Application / Permit
- 20014-20000-00264
- Plan Check / Job No.
- B20VN00993
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 23'-10" X 30'-9" IRREGULAR ADDITION TO (E) DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). RE-FRAME / RE-ROOF. WORK PER WFPP.
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Green Plans Picked Up | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | ROSENDO MEDINA |
| Corrections Issued | 3/11/2020 | ROSENDO MEDINA |
| Quality Review Completed | 3/11/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 10/21/2021 | ROSENDO MEDINA |
| Plan Check Approved | 11/29/2021 | ROSENDO MEDINA |
| Building Plans Picked Up | 11/29/2021 | APPLICANT |
| Issued | 8/18/2022 | APPLICANT |
| CofO in Progress | 10/20/2025 | JENNIFER RABUCHIN |
| CofO Issued | 10/28/2025 | RUBEN SALAS |
| Permit Finaled | 10/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/18/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/18/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 8/12/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/12/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 9/1/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/18/2021 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/2/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/17/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/17/2024 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 12/19/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/2/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 1/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/8/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 1/8/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 1/8/2025 | Conditional Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/14/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/14/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/14/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 1/14/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/14/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/23/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/23/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 1/23/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 1/23/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 1/23/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 1/28/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 1/28/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 2/5/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 2/5/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 2/5/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/13/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/3/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Final | 9/3/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 9/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Final | 9/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Final | 9/3/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 9/3/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 9/3/2025 | SGSOV Not Required | NICHOLAS TROWBRIDGE |
| Service/Power Release | 9/3/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 9/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 9/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/5/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 9/5/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/5/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 9/5/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/23/2025 | Approved | JENNIFER RABUCHIN |
| Final | 9/23/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 9/23/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 10/20/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 10/20/2025 | Approved | JENNIFER RABUCHIN |