6638 N CLEON AVE 91606
Certificate Information: 6638 N CLEON AVE 91606
- Application / Permit
- 20014-20000-00257
- Plan Check / Job No.
- B20VN00975
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (16'-9" X 26'-7") RECROOM ADDITION TO THE (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 2/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/22/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 1/22/2020 | ARTIN ZARUKIAN |
| Plan Check Approved | 2/3/2020 | TROY DEGUZMAN |
| Issued | 2/3/2020 | LADBS |
| CofO in Progress | 10/14/2020 | DANIEL DREW |
| No Progress | 1/9/2021 | MICHAEL SMITH |
| CofO in Progress | 2/1/2021 | MICHAEL SMITH |
| Permit Finaled | 2/1/2021 | MICHAEL SMITH |
| CofO Issued | 2/1/2021 | MICHAEL SMITH |
| Permit Finaled | 2/1/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 2/3/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/3/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/13/2020 | Approved | RAYMOND KEHOE |
| Footing/Foundation/Slab | 3/13/2020 | Corrections Issued | RAYMOND KEHOE |
| Footing/Foundation/Slab | 3/24/2020 | Conditional Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 6/5/2020 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/9/2020 | Approved | DANIEL DREW |
| Deputy Wood Construction | 6/9/2020 | Conditional Approval | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Approved | DANIEL DREW |
| Green Building Rough | 6/9/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 6/19/2020 | Approved | DANIEL DREW |
| Insulation | 6/25/2020 | Approved | RAYMOND KEHOE |
| Drywall Nailing | 6/30/2020 | Approved | RAYMOND KEHOE |
| Final | 9/17/2020 | Corrections Issued | DANIEL DREW |
| Footing/Foundation/Slab | 9/17/2020 | Approved | DANIEL DREW |
| Green Building Final | 9/17/2020 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 9/17/2020 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 9/17/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 10/1/2020 | Approved | DANIEL DREW |
| Final | 10/1/2020 | Conditional Approval | DANIEL DREW |
| HVAC-Final | 10/1/2020 | Approved | DANIEL DREW |
| PLUMBING-Final | 10/1/2020 | Approved | DANIEL DREW |
| Final | 10/13/2020 | OK to Issue CofO | DANIEL DREW |