15446 W SAN JOSE ST 91345
Certificate Information: 15446 W SAN JOSE ST 91345
- Application / Permit
- 20014-20000-00244
- Plan Check / Job No.
- B20VN00927
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE AND 19' X 26' IRR. SHAPED ADDITION TO CREATE (N) ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 6/11/2020
- Issuing Office
- Current Status
- CofO Issued on 4/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2020 | APPLICANT |
| Green Plans Picked Up | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | RAPHAEL ROSAS |
| Corrections Issued | 3/10/2020 | RAPHAEL ROSAS |
| Quality Review Completed | 3/10/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/11/2020 | APPLICANT |
| Plan Check Approved | 6/3/2020 | RAPHAEL ROSAS |
| Issued | 6/11/2020 | APPLICANT |
| CofO in Progress | 3/3/2022 | JENNIFER RABUCHIN |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
| CofO Issued | 4/2/2022 | DEROLD HAUFF |
| Permit Finaled | 4/2/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/7/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/7/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/8/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2021 | Partial Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 5/19/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/27/2021 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 6/4/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/1/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 7/1/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 7/1/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 7/1/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Gas Test | 7/2/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/2/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/14/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/28/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/28/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 7/28/2021 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 7/28/2021 | Approved | JENNIFER RABUCHIN |
| Sewer | 7/28/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/4/2021 | Approved | GREGG CUMMINGS |
| Insulation | 8/4/2021 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 8/4/2021 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 8/10/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/10/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/19/2021 | Corrections Issued | AMY COLIN |
| Shower Pan | 8/19/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 8/31/2021 | Approved | AMY COLIN |
| ELECTRICAL-Final | 10/27/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 10/27/2021 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/10/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/20/2021 | Not Ready for Inspection | JOHN HAYES |
| Gas Test | 12/28/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/28/2021 | Approved | JENNIFER RABUCHIN |
| Final | 2/23/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/23/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 2/23/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 2/23/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/23/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 2/23/2022 | Approved | JENNIFER RABUCHIN |
| Final | 3/4/2022 | OK to Issue CofO | JENNIFER RABUCHIN |