9728 N HAYVENHURST AVE 91343
Certificate Information: 9728 N HAYVENHURST AVE 91343
- Application / Permit
- 20014-20000-00236
- Plan Check / Job No.
- B20VN00915
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 17' 10" X 22' TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 5/26/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Green Plans Picked Up | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 3/7/2020 | GURUNATH NESARAJAH |
| Quality Review Completed | 3/12/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/13/2020 | APPLICANT |
| Plan Check Approved | 5/13/2020 | GURUNATH NESARAJAH |
| Issued | 5/26/2020 | LADBS |
| CofO in Progress | 5/6/2021 | MICHAEL TEMPLE |
| CofO Issued | 5/15/2021 | MICHAEL SMITH |
| Permit Finaled | 5/15/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/2/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 4/2/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/3/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 5/1/2020 | TIMOTHY POWELL |
| Green Code | Cleared | 5/12/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Barker Graham Lee; Lic. No.: 415983-B | 23746 BURTON ST WEST HILLS, CA 91304 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/4/2020 | Corrections Issued | BEAU COLLINS |
| PLUMBING-Rough | 6/4/2020 | Not Ready for Inspection | BEAU COLLINS |
| Excavation/Setback/Form/Re-Bar | 6/16/2020 | Not Ready for Inspection | BEAU COLLINS |
| PLUMBING-Rough | 6/16/2020 | Not Ready for Inspection | BEAU COLLINS |
| Excavation/Setback/Form/Re-Bar | 6/17/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/17/2020 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/27/2020 | No Access for Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 7/27/2020 | No Access for Inspection | PIERRE VEGA |
| Green Building Rough | 7/27/2020 | No Access for Inspection | PIERRE VEGA |
| HVAC-Rough | 7/27/2020 | No Access for Inspection | PIERRE VEGA |
| Interior/Exterior Lathing | 7/27/2020 | No Access for Inspection | PIERRE VEGA |
| PLUMBING-Rough | 7/27/2020 | No Access for Inspection | PIERRE VEGA |
| Rough-Elec/Plmb/HVAC | 7/27/2020 | No Access for Inspection | PIERRE VEGA |
| Wood Frame | 7/27/2020 | No Access for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 7/29/2020 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Rough | 7/29/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| Rough-Elec/Plmb/HVAC | 7/29/2020 | Corrections Issued | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 7/30/2020 | No Access for Inspection | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 7/30/2020 | No Access for Inspection | DANIEL DREW |
| BUILDING-Rough-Frame | 10/7/2020 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 10/7/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Rough-Elec/Plmb/HVAC | 10/7/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 11/12/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 11/12/2020 | Approved | ARTHUR SARGSYAN |
| Insulation | 11/12/2020 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 11/12/2020 | Approved | ARTHUR SARGSYAN |
| Final | 1/28/2021 | Partial Approval | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 1/28/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 1/28/2021 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 1/28/2021 | Approved | ARTHUR SARGSYAN |
| Final | 2/8/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Final | 4/26/2021 | OK to Issue CofO | MICHAEL TEMPLE |