3458 W CASITAS AVE 90039
Certificate Information: 3458 W CASITAS AVE 90039
- Application / Permit
- 20014-20000-00233
- Plan Check / Job No.
- B20VN00908
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (12'-6"x 16'-2") TO & CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT. WORK PER LA STD WFPP.
- Permit Issued
- Issued on 4/10/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Green Plans Picked Up | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | TROY DEGUZMAN |
| Corrections Issued | 3/7/2020 | TROY DEGUZMAN |
| Quality Review Completed | 3/11/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/16/2020 | APPLICANT |
| Applicant returned to address corrections | 3/26/2020 | TROY DEGUZMAN |
| Plan Check Approved | 4/6/2020 | TROY DEGUZMAN |
| Issued | 4/10/2020 | LADBS |
| CofO in Progress | 9/10/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
| CofO Issued | 9/29/2021 | DEROLD HAUFF |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 3/26/2020 | AARON COSTA |
| Address approval | Cleared | 3/31/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/31/2020 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 3/31/2020 | JOHN LIN |
| Sewer availability | Cleared | 3/31/2020 | JOHN LIN |
Contact Information
| Contractor | E G N Builders Group; Lic. No.: 1051430-B | 5000 PARKWAY CALABASAS SUITE 308 CALABASAS, CA 91302 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/16/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 7/28/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 9/14/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Pre-Inspection | 10/29/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 1/15/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 1/27/2021 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 2/3/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/9/2021 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 3/16/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 3/16/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Rough-Elec/Plmb/HVAC | 3/24/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 3/30/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/30/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/7/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/7/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/12/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 4/12/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 4/12/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/19/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 4/19/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/19/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 4/21/2021 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 4/21/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 5/3/2021 | Approved | HAMIK HARTOUNIAN |
| Wood Frame | 5/3/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 5/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/5/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/23/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 8/23/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 8/23/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 8/23/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/23/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 8/27/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 8/27/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/27/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/27/2021 | Approved | HAMIK HARTOUNIAN |