7925 N BEN AVE 91605
Certificate Information: 7925 N BEN AVE 91605
- Application / Permit
- 20014-20000-00232
- Plan Check / Job No.
- B20VN00907
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (52'-6"x 32'-0") IRR SHAPE TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Current Status
- Issued on 9/4/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/21/2020 | APPLICANT |
| Green Plans Picked Up | 2/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | TROY DEGUZMAN |
| Corrections Issued | 3/7/2020 | TROY DEGUZMAN |
| Quality Review Completed | 3/9/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/9/2020 | APPLICANT |
| Applicant returned to address corrections | 4/10/2020 | TROY DEGUZMAN |
| Plan Check Approved | 5/14/2020 | TROY DEGUZMAN |
| Issued | 9/4/2020 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 3/17/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 3/17/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 3/17/2020 | THOMAS LANG |
| Sewer availability | Cleared | 3/17/2020 | THOMAS LANG |
| Green Code | Cleared | 3/25/2020 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/24/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 6/24/2021 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 9/11/2025 | Corrections Issued | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 12/8/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Excavation/Setback/Form/Re-Bar | 12/8/2025 | Approved | MATTHEW NELSON |
| Underground Mechanical | 12/22/2025 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2025 | Partial Approval | CRAIG DAVIS |
| PLUMBING-Rough | 12/26/2025 | Partial Approval | CRAIG DAVIS |
| Pre-Inspection | 2/9/2026 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/17/2026 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 2/17/2026 | Approved | MATTHEW NELSON |
| Green Building Rough | 2/17/2026 | Approved | MATTHEW NELSON |
| HVAC-Rough | 2/17/2026 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 2/17/2026 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/25/2026 | Conditional Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/2/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/2/2026 | Partial Approval | MATTHEW NELSON |
| Insulation | 3/9/2026 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/9/2026 | Approved | MATTHEW NELSON |
| Shower Pan | 3/9/2026 | Approved | MATTHEW NELSON |
| Drywall Nailing | 3/13/2026 | Approved | DAVID MATSON |
| ELECTRICAL-Final | 5/8/2026 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 5/8/2026 | Corrections Issued | MATTHEW NELSON |