6013 1/2 N COLFAX AVE 91606
Certificate Information: 6013 1/2 N COLFAX AVE 91606
- Application / Permit
- 20014-20000-00211
- Plan Check / Job No.
- B20VN00846
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 20'-6" X 37' IRREGULAR SHAPE TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2020 | APPLICANT |
| Green Plans Picked Up | 2/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | SELLA BENYAMIN |
| Corrections Issued | 3/9/2020 | SELLA BENYAMIN |
| Quality Review Completed | 3/12/2020 | STEVEN KIM |
| Building Plans Picked Up | 3/13/2020 | APPLICANT |
| Plan Check Approved | 8/18/2021 | SELLA BENYAMIN |
| Issued | 9/17/2021 | APPLICANT |
| CofO in Progress | 4/3/2023 | DAVID ANDERSON |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/20/2020 | RIDWAN HARDY |
| Address approval | Cleared | 12/1/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/21/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/2/2021 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 7/28/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 7/29/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/11/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/9/2022 | Partial Approval | JOHN HAYES |
| Pre-Inspection | 9/9/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 9/19/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Approved | JOHN HAYES |
| HVAC-Rough | 11/2/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 11/2/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | JOHN HAYES |
| Green Building Rough | 11/7/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 11/7/2022 | Approved | JOHN HAYES |
| Insulation | 11/29/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 11/29/2022 | Partial Approval | JOHN HAYES |
| Insulation | 12/6/2022 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 12/6/2022 | Partial Approval | JOHN HAYES |
| Insulation | 12/14/2022 | Approved | JORDAN KUTZLY |
| Drywall Nailing | 12/23/2022 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 3/14/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/14/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 3/14/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 3/14/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 3/14/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/14/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/31/2023 | OK to Issue CofO | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 3/31/2023 | Approved | DAVID ANDERSON |