5227 N STROHM AVE 91601
Certificate Information: 5227 N STROHM AVE 91601
- Application / Permit
- 20014-20000-00193
- Plan Check / Job No.
- B20VN00758
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (N) 15'-11" X 17'- 3" BEDROOM TO (E) 28' X 16'-3" ACCESSORY DWELLING UNIT ALL WORK PER WFPP
- Permit Issued
- Issued on 7/31/2020
- Issuing Office
- Current Status
- Permit Finaled on 9/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Green Plans Picked Up | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/27/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 3/3/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 3/9/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/9/2020 | APPLICANT |
| Plan Check Approved | 7/31/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 7/31/2020 | APPLICANT |
| CofO in Progress | 7/20/2021 | DANIEL DREW |
| Permit Finaled | 9/4/2021 | MICHAEL PELHAM |
| No Progress | 9/4/2021 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/10/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 3/12/2020 | AARON COSTA |
| Low Impact Development | Cleared | 7/10/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/29/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/4/2020 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 10/13/2020 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 10/13/2020 | Partial Approval | DANIEL DREW |
| Footing/Foundation/Slab | 10/16/2020 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 10/20/2020 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2020 | Approved | DANIEL DREW |
| Shower Pan | 10/30/2020 | Not Ready for Inspection | DANIEL DREW |
| Interior/Exterior Lathing | 11/9/2020 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 11/25/2020 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 11/25/2020 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/2/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/2/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/8/2020 | Approved | DANIEL DREW |
| Green Building Rough | 12/8/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 12/8/2020 | Approved | DANIEL DREW |
| Insulation | 12/15/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 12/18/2020 | Not Ready for Inspection | DANIEL DREW |
| Sewer | 12/18/2020 | Approved | DANIEL DREW |
| Underground Mechanical | 12/18/2020 | Approved | DANIEL DREW |
| Interior/Exterior Lathing | 12/23/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 4/1/2021 | Approved | DANIEL DREW |
| Final | 4/1/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 4/1/2021 | Corrections Issued | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 4/1/2021 | SGSOV Not Ready | DANIEL DREW |
| Smoke Detectors | 4/1/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 4/16/2021 | Approved | DANIEL DREW |
| Final | 5/4/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 5/4/2021 | Approved | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Not Ready | DANIEL DREW |
| Final | 5/14/2021 | Not Ready for Inspection | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 5/14/2021 | SGSOV Approved | DANIEL DREW |
| Final | 6/30/2021 | Not Ready for Inspection | DANIEL DREW |
| Final | 7/19/2021 | OK to Issue CofO | DANIEL DREW |