16913 W VOSE ST 91406

Certificate Information: 16913 W VOSE ST 91406

Application / Permit
20014-20000-00192
Plan Check / Job No.
B20VN00757
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
24' X 21' ADDITION FOR MASTER BEDROOM, BATHROOM, LAUNDRY ROOM, AND CLOSET TO (E) SINGLE FAMILY DWELLING. ALL WORK PER WFPP. REMOVE (E) 18' x 22' ATTACHED PATIO COVER.
Permit Issued
Issued on 1/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2020 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 1/16/2020 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 1/17/2020 LUIS RINCON
Plan Check Approved 1/21/2020 ROSENDO MEDINA
Issued 1/21/2020 LADBS
CofO in Progress 8/19/2020 STEVEN BACK
Permit Finaled 9/2/2020 MICHAEL SMITH
CofO Issued 9/2/2020 MICHAEL SMITH
Permit Finaled 9/2/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/17/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/17/2020 ADRIAN CASTRO
Sewer availability Cleared 1/17/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/28/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 3/3/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 3/6/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 3/25/2020 Partial Approval STEVEN BACK
PLUMBING-Rough 3/25/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/28/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 5/8/2020 Approved STEVEN BACK
ELECTRICAL-Rough 5/8/2020 Approved STEVEN BACK
Green Building Rough 5/8/2020 Corrections Issued STEVEN BACK
HVAC-Rough 5/8/2020 Approved STEVEN BACK
PLUMBING-Rough 5/8/2020 Approved STEVEN BACK
Green Building Rough 5/20/2020 Approved STEVEN BACK
Insulation 5/20/2020 Approved STEVEN BACK
Interior/Exterior Lathing 5/20/2020 Partial Approval STEVEN BACK
Drywall Nailing 5/26/2020 Approved STEVEN BACK
HVAC-Final 5/28/2020 Not Ready for Inspection STEVEN BACK
Shower Pan 5/28/2020 Approved STEVEN BACK
Special/Order Compliance 5/28/2020 Approved STEVEN BACK
Interior/Exterior Lathing 6/10/2020 Approved STEVEN BACK
ELECTRICAL-Final 8/19/2020 Approved STEVEN BACK
Final 8/19/2020 OK to Issue CofO STEVEN BACK
Green Building Final 8/19/2020 Approved STEVEN BACK
PLUMBING-Final 8/19/2020 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/19/2020 SGSOV Approved STEVEN BACK
Smoke Detectors 8/19/2020 Approved STEVEN BACK