2605 N ROKEBY ST 90039

Certificate Information: 2605 N ROKEBY ST 90039

Application / Permit
20014-20000-00191
Plan Check / Job No.
B20VN00751
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 25'-10"X 17'-10" ADDITION TO (E) 18'-2" X 17'-10" GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/14/2020
Issuing Office
Current Status
CofO Issued on 2/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 3/2/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 3/11/2020 OMID HEDAYAT
Building Plans Picked Up 3/17/2020 APPLICANT
Green Plans Picked Up 4/1/2020 APPLICANT
Plan Check Approved 8/11/2020 SEWADA ZADOORAN MILAGARDI
Issued 8/14/2020 APPLICANT
CofO in Progress 2/2/2021 JOSEPH MCGARRY
Permit Finaled 2/2/2021 DEROLD HAUFF
CofO Issued 2/2/2021 DEROLD HAUFF
Permit Finaled 2/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 3/26/2020 LAUREN PADICK
Address approval Cleared 4/3/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 4/3/2020 JEANIE LAM
Green Code Cleared 4/7/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 4/7/2020 GILBERT URREA
Miscellaneous Cleared 6/5/2020 TERRY PHAN
Eng Process Fee Ord 176,300 Cleared 8/7/2020 JEANIE LAM
Sewer availability Cleared 8/7/2020 JEANIE LAM
Construction near power lines Cleared 8/10/2020 WALTER RAMIREZ

Contact Information

Contractor P M A Renovations; Lic. No.: 1033506-B 17941 VENTURA BLVD #204      ENCINO, CA 91316

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/8/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 9/15/2020 Approved JOSEPH MCGARRY
Deputy Wood Construction 9/24/2020 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 10/15/2020 Approved JOSEPH MCGARRY
HVAC-Rough 10/15/2020 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/15/2020 Approved JOSEPH MCGARRY
Wood Frame 10/15/2020 Approved JOSEPH MCGARRY
Gas Test 10/22/2020 Not Ready for Inspection JOSEPH MCGARRY
Interior/Exterior Lathing 10/22/2020 Partial Approval JOSEPH MCGARRY
Shower Pan 10/22/2020 Approved JOSEPH MCGARRY
Insulation 10/27/2020 Approved JOSEPH MCGARRY
Underground Mechanical 10/27/2020 Not Ready for Inspection JOSEPH MCGARRY
Drywall Nailing 11/4/2020 Approved JOSEPH MCGARRY
Gas Test 11/4/2020 Approved JOSEPH MCGARRY
Green Building Rough 11/4/2020 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 11/4/2020 Approved JOSEPH MCGARRY
Sewer 11/4/2020 Approved JOSEPH MCGARRY
Underground Mechanical 11/4/2020 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 12/23/2020 Approved HAMIK HARTOUNIAN
Final 12/23/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 12/23/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Not Ready DAVID FEILER
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 12/23/2020 Approved HAMIK HARTOUNIAN
Final 1/29/2021 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 1/29/2021 SGSOV Approved JOSEPH MCGARRY