7821 N BELLAIRE AVE 91605
Certificate Information: 7821 N BELLAIRE AVE 91605
- Application / Permit
- 20014-20000-00176
- Plan Check / Job No.
- B20VN00684
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL - REMOVE (E) SFD W/ (E) GARAGE TO REMAIN AND ADD 33'-0" X 38'-0" 2-STORY SFD W/ 5'-2" X 12'-6" FRONT PORCH AND 17'-2" X 24'-0" TRELLIS. ALL WORK PER ENGINEERING. [NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT]
- Permit Issued
- Issued on 9/18/2020
- Issuing Office
- Current Status
- CofO Issued on 9/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | JENNIFER LEE |
| Corrections Issued | 1/29/2020 | JENNIFER LEE |
| Quality Review Completed | 1/30/2020 | STEVEN KIM |
| Building Plans Picked Up | 2/3/2020 | APPLICANT |
| Green Plans Picked Up | 2/4/2020 | APPLICANT |
| Applicant returned to address corrections | 8/17/2020 | JENNIFER LEE |
| Plan Check Approved | 9/16/2020 | JENNIFER LEE |
| Issued | 9/18/2020 | APPLICANT |
| CofO in Progress | 5/28/2021 | GREGG CUMMINGS |
| CofO Issued | 9/18/2021 | MICHAEL SMITH |
| Permit Finaled | 9/18/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2020 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 2/25/2020 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 6/15/2020 | AARON COSTA |
| Low Impact Development | Cleared | 6/17/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/23/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 7/31/2020 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/21/2020 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/24/2020 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/29/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 10/7/2020 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/9/2020 | Partial Approval | GREGG CUMMINGS |
| Insulation | 10/9/2020 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/16/2020 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 10/16/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/30/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 10/30/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Deputy Wood Construction | 11/4/2020 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 11/16/2020 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 11/18/2020 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/25/2020 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 12/2/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 12/2/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/22/2020 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 12/22/2020 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/22/2020 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/31/2020 | Approved | GREGG CUMMINGS |
| Shower Pan | 12/31/2020 | Approved | GREGG CUMMINGS |
| Insulation | 1/6/2021 | Approved | MATTHEW NELSON |
| Drywall Nailing | 1/13/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/13/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 3/24/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Final | 3/24/2021 | Approved | GREGG CUMMINGS |
| Green Building Final | 3/31/2021 | Approved | GREGG CUMMINGS |
| HVAC-Final | 3/31/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 5/6/2021 | Approved | GREGG CUMMINGS |
| Final | 5/6/2021 | Corrections Issued | GREGG CUMMINGS |
| Gas Test | 5/6/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 5/6/2021 | Approved | GREGG CUMMINGS |
| Final | 5/27/2021 | OK to Issue CofO | GREGG CUMMINGS |
| Service/Power Release | 5/27/2021 | Approved | GREGG CUMMINGS |
| Pool/Spa Cover | 8/3/2021 | Not Ready for Inspection | GREGG CUMMINGS |