626 N GULF AVE 90744

Certificate Information: 626 N GULF AVE 90744

Application / Permit
20014-20000-00174
Plan Check / Job No.
B20VN00681
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 43'-6"X 32' IRREGULAR SHAPED ADDITION TO (E) 15' X 20' GARAGE AND CONVERT ENTIRE BUILDING TO ACCESSORY DWELLING UNIT ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/23/2020
Issuing Office
Current Status
CofO Issued on 5/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2020 APPLICANT
Green Plans Picked Up 2/20/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 3/5/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 3/11/2020 STEVEN KIM
Building Plans Picked Up 3/13/2020 APPLICANT
Plan Check Approved 6/22/2020 SEWADA ZADOORAN MILAGARDI
Issued 6/23/2020 APPLICANT
CofO in Progress 4/30/2021 ANSON MAGLASANG
CofO in Progress 5/3/2021 JOHN KLARIN
Permit Finaled 5/6/2021 DEROLD HAUFF
CofO Issued 5/6/2021 DEROLD HAUFF
Permit Finaled 5/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 5/6/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/8/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 5/12/2020 THOMAS LANG
Sewer availability Cleared 5/12/2020 THOMAS LANG
Address approval Cleared 5/15/2020 THOMAS LANG
Clean Up Green Up Cleared 5/15/2020 LAUREN PADICK
Green Code Cleared 5/19/2020 MICHAEL AYERS

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/23/2020 Conditional Approval JOHN KLARIN
Underground Mechanical 7/23/2020 Not Ready for Inspection JOHN KLARIN
Deputy Drilled-In Anchors 7/28/2020 Approved JOHN KLARIN
Excavation/Setback/Form/Re-Bar 7/29/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/10/2020 Conditional Approval JOHN KLARIN
Insulation 8/10/2020 Not Ready for Inspection JOHN KLARIN
Underground Mechanical 8/10/2020 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Approved JOHN KLARIN
ELECTRICAL-Final 8/19/2020 Not Ready for Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/22/2020 Partial Inspection JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 9/29/2020 Approved JOHN KLARIN
BUILDING-Rough-Frame 11/6/2020 Approved JOHN KLARIN
ELECTRICAL-Rough 11/6/2020 Approved JOHN KLARIN
Green Building Rough 11/6/2020 Approved JOHN KLARIN
HVAC-Rough 11/6/2020 Approved JOHN KLARIN
METHANE-Rough 11/6/2020 Approved JOHN KLARIN
PLUMBING-Rough 11/6/2020 Corrections Issued JOHN KLARIN
ELECTRICAL-Rough 11/18/2020 Approved JOHN KLARIN
Interior/Exterior Lathing 11/18/2020 Approved JOHN KLARIN
PLUMBING-Rough 11/18/2020 Approved JOHN KLARIN
Insulation 11/23/2020 Approved ANSON MAGLASANG
Drywall Nailing 12/16/2020 Corrections Issued WILLIAM ROSE
Drywall Nailing 12/22/2020 Approved WILLIAM ROSE
Interior/Exterior Lathing 1/8/2021 Approved JOHN KLARIN
Final 4/12/2021 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 4/12/2021 Approved JOHN KLARIN
Green Building Final 4/12/2021 Approved JOHN KLARIN
METHANE-Barrier 4/12/2021 Approved JOHN KLARIN
METHANE-Subgrade 4/12/2021 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 4/12/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 4/12/2021 Approved JOHN KLARIN
Final 4/21/2021 Corrections Issued JOHN KLARIN
Final 4/22/2021 OK to Issue CofO JOHN KLARIN
Service/Power Release 4/22/2021 Approved JOHN KLARIN
Final 4/30/2021 OK to Issue CofO JOHN KLARIN