13320 W CHANDLER BLVD 91401
Certificate Information: 13320 W CHANDLER BLVD 91401
- Application / Permit
- 20014-20000-00171
- Plan Check / Job No.
- B20VN00673
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) 17'-5" X 17'-1" 2ND FLOOR, REMODEL, 5'-11" X 18'-7" & 8'-10" X 13'-1" ADDITION AT FIRST FLOOR AND 55'-5" X 66'-4" (IRREGULAR SHAPED) 2ND STORY ADDITION TO (E) SFD.
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- CofO Issued on 3/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 1/25/2020 | ARTIN ZARUKIAN |
| Quality Review Completed | 1/27/2020 | STEVEN KIM |
| Building Plans Picked Up | 2/10/2020 | APPLICANT |
| Green Plans Picked Up | 2/10/2020 | APPLICANT |
| Applicant returned to address corrections | 2/28/2020 | ARTIN ZARUKIAN |
| Plan Check Approved | 9/10/2020 | ARTIN ZARUKIAN |
| Issued | 9/10/2020 | APPLICANT |
| CofO in Progress | 10/6/2021 | MISAEL ESPARZA |
| CofO Issued | 3/9/2022 | MICHAEL SMITH |
| Permit Finaled | 3/9/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/14/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 3/12/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 7/21/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/27/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Bellagio Design Build Corporation; Lic. No.: 935571-B | 19336 CALVERT STREET TARZANA, CA 91335 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/15/2020 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/15/2020 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/23/2020 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2020 | Approved | DANIEL DREW |
| Green Building Rough | 11/6/2020 | Not Ready for Inspection | DANIEL DREW |
| Sewer | 11/6/2020 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2020 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 12/8/2020 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 12/8/2020 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 12/21/2020 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 12/21/2020 | Partial Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/4/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 1/4/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/26/2021 | Corrections Issued | CHARLES POWELL |
| Green Building Rough | 1/26/2021 | Not Ready for Inspection | CHARLES POWELL |
| Wood Frame | 1/26/2021 | Not Ready for Inspection | CHARLES POWELL |
| Interior/Exterior Lathing | 2/4/2021 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 2/8/2021 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 2/8/2021 | Approved | CHARLES POWELL |
| Insulation | 2/10/2021 | Approved | CHARLES POWELL |
| Drywall Nailing | 2/16/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/16/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/16/2021 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 2/16/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/18/2021 | Partial Approval | ARAM AVEDISIAN |
| Final | 7/7/2021 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Final | 7/7/2021 | Not Ready for Inspection | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 7/7/2021 | SGSOV Not Ready | CHARLES POWELL |
| Smoke Detectors | 7/7/2021 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Final | 10/5/2021 | Approved | MISAEL ESPARZA |
| Final | 10/5/2021 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 10/5/2021 | Approved | MISAEL ESPARZA |
| HVAC-Final | 10/5/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 10/5/2021 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/5/2021 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 10/5/2021 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 10/5/2021 | Approved | MISAEL ESPARZA |