4500 N MORELLA AVE 91607

Certificate Information: 4500 N MORELLA AVE 91607

Application / Permit
20014-20000-00165
Plan Check / Job No.
B20VN00645
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 10'-5.5" x 16'-0" ADDITION OF A BATHROOM AND A CLOSET TO THE (E) SINGLE FAMILY DWELLING. ALL WORK PER WFPP.
Permit Issued
Issued on 6/30/2021
Issuing Office
Current Status
CofO Issued on 8/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2020 APPLICANT
Assigned to Plan Check Engineer 1/15/2020 SERGIO MUNIZ
Corrections Issued 1/15/2020 SERGIO MUNIZ
Plan Check Approved 9/16/2020 SARKIS HARABEDIAN
No Progress 5/2/2021 SARKIS HARABEDIAN
Plan Check Approved 5/2/2021 SARKIS HARABEDIAN
Building Plans Picked Up 5/14/2021 APPLICANT
Issued 6/30/2021 APPLICANT
CofO in Progress 6/15/2022 THOMAS FINNILA
CofO in Progress 6/15/2022 THOMAS FINNILA
Permit Finaled 8/25/2022 DANIEL ORRANTE
CofO Issued 8/25/2022 DANIEL ORRANTE
Permit Finaled 8/25/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/26/2020 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 2/26/2020 MARKOS PEREZ-BRAN
ZI Cleared 2/26/2020 DANG NGUYEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/15/2021 Approved ARTHUR SARGSYAN
Deputy Drilled-In Anchors 9/24/2021 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 9/24/2021 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/4/2021 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 11/1/2021 Partial Approval THOMAS FINNILA
Wood Frame 11/1/2021 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 12/1/2021 Corrections Issued THOMAS FINNILA
Gas Test 12/7/2021 Approved THOMAS FINNILA
ELECTRICAL-Rough 3/3/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/3/2022 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 3/3/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 3/8/2022 Not Ready for Inspection RYAN SALAZAR
Gas Test 3/8/2022 Approved RYAN SALAZAR
Green Building Rough 3/8/2022 Not Ready for Inspection RYAN SALAZAR
MERV13>=Rough 3/8/2022 Not Ready for Inspection RYAN SALAZAR
Rough-Elec/Plmb/HVAC 3/8/2022 Approved RYAN SALAZAR
Green Building Rough 3/17/2022 Approved MATTHEW NELSON
Insulation 3/17/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/17/2022 Approved MATTHEW NELSON
Shower Pan 3/17/2022 Approved MATTHEW NELSON
Drywall Nailing 4/5/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 4/5/2022 Approved THOMAS FINNILA
Smoke Detectors 5/25/2022 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/31/2022 Approved CHRISTOPHER DELLEFIELD
Final 5/31/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 5/31/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Final 5/31/2022 Approved CHRISTOPHER DELLEFIELD
MERV13>=Final 5/31/2022 Approved CHRISTOPHER DELLEFIELD
MERV13>=Rough 5/31/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 5/31/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Final 6/13/2022 OK to Issue CofO THOMAS FINNILA
Smoke Detectors 6/13/2022 Approved THOMAS FINNILA