410 E MANITOBA ST 90293
Certificate Information: 410 E MANITOBA ST 90293
- Application / Permit
- 20014-20000-00141
- Plan Check / Job No.
- B20VN00563
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED CARPORT TO BEDROOM AND ADD NEW 20' X 20' TWO-CAR ATTACHED GARAGE. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2020 | SEAN SHAHMIRI |
| Corrections Issued | 1/14/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/15/2020 | ROSENDO MEDINA |
| Plan Check Approved | 3/10/2020 | GURUNATH NESARAJAH |
| Issued | 3/12/2020 | LADBS |
| CofO in Progress | 3/24/2023 | BOBBY KEY |
| Permit Finaled | 4/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/6/2023 | DANIEL ORRANTE |
| CofO Issued | 4/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 1/14/2020 | BARTON HOLMES |
| Roof/Waste drainage to street | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/14/2020 | LEE GUILBEAUX |
| Coastal Zone | Cleared | 3/10/2020 | SHEILA GERSHON |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/20/2020 | Corrections Issued | JUAN VALENZUELA |
| METHANE-Barrier | 3/20/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Subgrade | 3/20/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/27/2020 | Partial Approval | JUAN VALENZUELA |
| Pre-Inspection | 3/27/2020 | Partial Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2020 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/8/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 4/8/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Rough | 4/8/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Special/Order Compliance | 4/8/2020 | Approved | JUAN VALENZUELA |
| Special/Order Compliance | 4/23/2020 | Conditional Approval | JUAN VALENZUELA |
| Insulation | 5/12/2020 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 5/12/2020 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 5/29/2020 | Approved | DAVID HEINE |
| Green Building Rough | 5/29/2020 | Approved | DAVID HEINE |
| Insulation | 5/29/2020 | Approved | DAVID HEINE |
| Smoke Detectors | 5/29/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 6/2/2020 | Approved | JUAN VALENZUELA |
| Final | 6/23/2020 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 6/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Final | 6/23/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 6/23/2020 | SGSOV Not Ready | JUAN VALENZUELA |
| ELECTRICAL-Final | 6/25/2020 | Approved | JUAN VALENZUELA |
| Final | 6/25/2020 | Conditional Approval | JUAN VALENZUELA |
| Green Building Final | 6/25/2020 | Approved | JUAN VALENZUELA |
| HVAC-Final | 6/25/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 6/25/2020 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 6/25/2020 | SGSOV Approved | JUAN VALENZUELA |
| Final | 3/24/2023 | OK to Issue CofO | BOBBY KEY |