410 E MANITOBA ST 90293

Certificate Information: 410 E MANITOBA ST 90293

Application / Permit
20014-20000-00141
Plan Check / Job No.
B20VN00563
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED CARPORT TO BEDROOM AND ADD NEW 20' X 20' TWO-CAR ATTACHED GARAGE. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 3/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2020 SEAN SHAHMIRI
Corrections Issued 1/14/2020 SEAN SHAHMIRI
Applicant returned to address corrections 1/15/2020 ROSENDO MEDINA
Plan Check Approved 3/10/2020 GURUNATH NESARAJAH
Issued 3/12/2020 LADBS
CofO in Progress 3/24/2023 BOBBY KEY
Permit Finaled 4/6/2023 DANIEL ORRANTE
Permit Finaled 4/6/2023 DANIEL ORRANTE
CofO Issued 4/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/14/2020 LEE GUILBEAUX
Grading Pre-Inspection Cleared 1/14/2020 BARTON HOLMES
Roof/Waste drainage to street Cleared 1/14/2020 LEE GUILBEAUX
Sewer availability Cleared 1/14/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/14/2020 LEE GUILBEAUX
Coastal Zone Cleared 3/10/2020 SHEILA GERSHON

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/20/2020 Corrections Issued JUAN VALENZUELA
METHANE-Barrier 3/20/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Subgrade 3/20/2020 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/27/2020 Partial Approval JUAN VALENZUELA
Pre-Inspection 3/27/2020 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/8/2020 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/8/2020 Approved JUAN VALENZUELA
Green Building Rough 4/8/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Rough 4/8/2020 Not Ready for Inspection JUAN VALENZUELA
Special/Order Compliance 4/8/2020 Approved JUAN VALENZUELA
Special/Order Compliance 4/23/2020 Conditional Approval JUAN VALENZUELA
Insulation 5/12/2020 Corrections Issued CRAIG DAVIS
Interior/Exterior Lathing 5/12/2020 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 5/29/2020 Approved DAVID HEINE
Green Building Rough 5/29/2020 Approved DAVID HEINE
Insulation 5/29/2020 Approved DAVID HEINE
Smoke Detectors 5/29/2020 Approved DAVID HEINE
Drywall Nailing 6/2/2020 Approved JUAN VALENZUELA
Final 6/23/2020 Corrections Issued JUAN VALENZUELA
Green Building Final 6/23/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Final 6/23/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/23/2020 SGSOV Not Ready JUAN VALENZUELA
ELECTRICAL-Final 6/25/2020 Approved JUAN VALENZUELA
Final 6/25/2020 Conditional Approval JUAN VALENZUELA
Green Building Final 6/25/2020 Approved JUAN VALENZUELA
HVAC-Final 6/25/2020 Approved JUAN VALENZUELA
PLUMBING-Final 6/25/2020 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/25/2020 SGSOV Approved JUAN VALENZUELA
Final 3/24/2023 OK to Issue CofO BOBBY KEY