1916 N NORMANDIE AVE 90027
Certificate Information: 1916 N NORMANDIE AVE 90027
- Application / Permit
- 20014-20000-00126
- Plan Check / Job No.
- B20VN00479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- CONVERT DETACHED GARAGE TO REC ROOM W/ HALF BATHROOM AND ADD 18'-0" X 5'-0" TO ENLARGE REC ROOM. ADD 18'-0" X 18'-0" CARPORT.
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 5/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 1/13/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 1/16/2020 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/16/2020 | APPLICANT |
| Issued | 1/24/2020 | LADBS |
| CofO in Progress | 5/1/2023 | JEFFREY MEAD |
| CofO Issued-Status Void | 5/5/2023 | DEROLD HAUFF |
| Permit Finaled-Status Void | 5/5/2023 | DEROLD HAUFF |
| Re-Activate Permit | 5/8/2023 | DEROLD HAUFF |
| CofO Corrected | 5/8/2023 | DEROLD HAUFF |
| Permit Finaled | 5/8/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/15/2020 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 1/16/2020 | JEROME MAGAT PALMA |
| Miscellaneous | Cleared | 1/16/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 1/16/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/1/2021 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/1/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/1/2021 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 6/1/2021 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 6/3/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/29/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 7/6/2021 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 9/24/2021 | Approved | WILLIAM WREN |
| Special/Order Compliance | 10/4/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/9/2022 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/9/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 3/9/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 3/9/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/9/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/14/2022 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/14/2022 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 3/14/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/14/2022 | Approved | JOSEPH MCGARRY |
| Sewer | 3/14/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 4/6/2022 | Approved | ADAM ESCOTO |
| Green Building Rough | 4/6/2022 | Approved | ADAM ESCOTO |
| Insulation | 4/6/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | ADAM ESCOTO |
| Drywall Nailing | 4/12/2022 | Approved | CRAIG DAVIS |
| Drywall Nailing | 4/13/2022 | Approved | RUBEN SALAS |
| Shower Pan | 4/28/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 7/21/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 7/21/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 7/21/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Final | 7/21/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 7/21/2022 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Final | 2/27/2023 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 2/27/2023 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 2/27/2023 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 2/27/2023 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 5/1/2023 | Approved | JEFFREY MEAD |
| Final | 5/1/2023 | OK to Issue CofO | JEFFREY MEAD |
| HVAC-Final | 5/1/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 5/1/2023 | Approved | JEFFREY MEAD |