4506 N MORELLA AVE 91607
Certificate Information: 4506 N MORELLA AVE 91607
- Application / Permit
- 20014-20000-00113
- Plan Check / Job No.
- B20VN00453
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 10'-2" X 17'-11" AND 12' X 25' ADDITION TO EXISTING SINGLE FAMILY DWELLING; INTERIOR REMODEL; RECONFIGURE FLOOR PLAN
- Permit Issued
- Issued on 7/9/2021
- Issuing Office
- Current Status
- CofO Issued on 2/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2020 | APPLICANT |
| Green Plans Picked Up | 2/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | SELLA BENYAMIN |
| Corrections Issued | 2/24/2020 | SELLA BENYAMIN |
| Quality Review Completed | 2/25/2020 | STEVEN KIM |
| Building Plans Picked Up | 2/27/2020 | APPLICANT |
| Applicant returned to address corrections | 4/27/2021 | SELLA BENYAMIN |
| Plan Check Approved | 5/14/2021 | SELLA BENYAMIN |
| Issued | 7/9/2021 | APPLICANT |
| CofO in Progress | 1/18/2023 | RYAN SALAZAR |
| CofO Issued | 2/13/2023 | MICHAEL SMITH |
| Permit Finaled | 2/13/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 4/1/2020 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 9/9/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 10/22/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/7/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/15/2021 | Approved | ARTHUR SARGSYAN |
| Sewer | 8/2/2021 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/9/2021 | Partial Approval | THOMAS FINNILA |
| Sewer | 8/9/2021 | Partial Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 9/24/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/24/2021 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/4/2021 | Conditional Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/25/2021 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 10/25/2021 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2021 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 11/12/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/17/2021 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/18/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2022 | Partial Inspection | MATT KELLERMAN |
| PLUMBING-Rough | 1/18/2022 | Corrections Issued | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 2/16/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 2/25/2022 | Partial Approval | THOMAS FINNILA |
| Deputy Wood Construction | 2/28/2022 | Conditional Approval | CALEB MEISTER |
| Deputy Wood Construction | 3/9/2022 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 4/20/2022 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 4/20/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 5/2/2022 | Approved | THOMAS FINNILA |
| Shower Pan | 5/2/2022 | Corrections Issued | THOMAS FINNILA |
| Service/Power Release | 5/12/2022 | Not Ready for Inspection | DAVID MATSON |
| Shower Pan | 5/12/2022 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 12/21/2022 | Not Ready for Inspection | DAVID MATSON |
| ELECTRICAL-Final | 12/21/2022 | Corrections Issued | DAVID MATSON |
| Final | 12/21/2022 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 12/21/2022 | Approved | DAVID MATSON |
| Green Building Final | 12/21/2022 | Approved | DAVID MATSON |
| Green Building Rough | 12/21/2022 | Approved | DAVID MATSON |
| MERV13>=Final | 12/21/2022 | Not Ready for Inspection | DAVID MATSON |
| MERV13>=Rough | 12/21/2022 | Corrections Issued | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 12/21/2022 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 12/27/2022 | Approved | JACK KARGODORIAN |
| Final | 12/27/2022 | Corrections Issued | JACK KARGODORIAN |
| MERV13>=Final | 12/27/2022 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 12/27/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 1/17/2023 | Approved | RYAN SALAZAR |
| Final | 1/17/2023 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 1/17/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 1/17/2023 | Approved | RYAN SALAZAR |