4533 N VESPER AVE 91403

Certificate Information: 4533 N VESPER AVE 91403

Application / Permit
20014-20000-00104
Plan Check / Job No.
B20VN00435
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR 16'4" LF AT NORTH SIDE AND BUILD AN IRREGULAR SHAPED 82'4" X 40' ONE STORY SINGLE FAMILY DWELLING WITH AN ATTACHED 20' X 19'11" TWO CAR GARAGE AND WITH NEW 20' X 9' REAR PATIO, NFPA-13D FIRE SPRINKLERS THROUGHOUT REQUIRED, ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/17/2020
Issuing Office
Current Status
CofO Issued on 6/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 RARES BODEA
Corrections Issued 2/27/2020 RARES BODEA
Quality Review Completed 3/4/2020 GUANG MIN TUNG
Building Plans Picked Up 3/6/2020 APPLICANT
Green Plans Picked Up 3/6/2020 APPLICANT
Plan Check Approved 8/17/2020 RARES BODEA
Issued 8/17/2020 APPLICANT
CofO in Progress 5/17/2021 CHARLES POWELL
Permit Finaled 6/12/2021 MICHAEL SMITH
CofO Issued 6/12/2021 MICHAEL SMITH
Permit Finaled 6/12/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/16/2020 JOHN TRIANTAFYLLOS
Permit Cleared 4/16/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 4/16/2020 JOHN TRIANTAFYLLOS
Trees in Parkway Cleared 4/29/2020 JOHN KIM
Low Impact Development Cleared 6/22/2020 SARAH YOUSSEF
Hydrant and Access approval Cleared 7/1/2020 KURT CORRAL
Roof/Waste drainage to street Cleared 7/2/2020 GABRIEL ROBLES
Green Code Cleared 7/14/2020 MICHAEL AYERS
ZI Cleared 7/16/2020 PABLO ESTRADA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/13/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 10/19/2020 Approved CHARLES POWELL
Special/Order Compliance 10/30/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 11/24/2020 Approved CHARLES POWELL
PLUMBING-Rough 11/24/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 12/11/2020 Approved CHARLES POWELL
Green Building Rough 12/11/2020 Not Ready for Inspection CHARLES POWELL
HVAC-Rough 12/11/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 12/11/2020 Partial Approval CHARLES POWELL
Shower Pan 12/11/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 12/16/2020 Partial Approval CHARLES POWELL
Drywall Nailing 12/28/2020 Approved CHARLES POWELL
Green Building Rough 12/28/2020 Approved CHARLES POWELL
Grounding or Bonding 2/5/2021 Partial Inspection ARTHUR SARGSYAN
Special/Order Compliance 2/5/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 4/5/2021 Approved CHARLES POWELL
PLUMBING-Final 4/5/2021 Approved CHARLES POWELL
Final 4/26/2021 Corrections Issued CHARLES POWELL
Green Building Final 4/26/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Approved CHARLES POWELL
Service/Power Release 4/26/2021 Approved CHARLES POWELL
Smoke Detectors 4/26/2021 Approved CHARLES POWELL
Final 5/17/2021 OK to Issue CofO CHARLES POWELL