8044 N MORSE AVE 91605

Certificate Information: 8044 N MORSE AVE 91605

Application / Permit
20014-20000-00094
Plan Check / Job No.
B20VN00393
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add 8.5' x 18' attached carport and 3.92' x 6' patio cover; convert attached garage with 41'2" x 14'9" iregular shape addition for bathroom, living room and relocated kitchen. All works are per design
Permit Issued
Issued on 2/19/2020
Issuing Office
Valley
Current Status
Issued on 2/19/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/10/2020 APPLICANT
Assigned to Plan Check Engineer 1/10/2020 HAYATO TSUCHIYA
Corrections Issued 1/10/2020 HAYATO TSUCHIYA
Plan Check Approved 2/18/2020 ALDOUS CHIC
Issued 2/19/2020 LADBS

Permit Application Clearance Information

Address approval Cleared 2/7/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/14/2020 JEANETTE VONG
Low Impact Development Cleared 2/14/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/14/2020 JEANETTE VONG
Sewer availability Cleared 2/14/2020 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2020 Partial Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 3/5/2020 Partial Inspection WILLIAM KUEHN
Footing/Foundation/Slab 3/5/2020 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 3/5/2020 Partial Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 4/14/2020 Partial Approval WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 4/14/2020 Approved WILLIAM KUEHN
Insulation 4/16/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 4/16/2020 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 4/16/2020 Not Ready for Inspection GREGG CUMMINGS
Drywall Nailing 4/21/2020 Approved WILLIAM KUEHN
Green Building Rough 4/21/2020 Approved WILLIAM KUEHN