23023 W SATICOY ST 91304
Certificate Information: 23023 W SATICOY ST 91304
- Application / Permit
- 20014-20000-00087
- Plan Check / Job No.
- B20VN00380
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 6'9"X21'6" ADDITION & CONVERT 21'2"X21'6" GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK PER WFPP
- Permit Issued
- Issued on 4/22/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2020 | APPLICANT |
| Green Plans Picked Up | 2/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | MARVEL DELACRUZ |
| Corrections Issued | 2/23/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 2/26/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/26/2020 | APPLICANT |
| Applicant returned to address corrections | 3/20/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 4/9/2020 | MARVEL DELACRUZ |
| Issued | 4/22/2020 | LADBS |
| CofO in Progress | 9/2/2020 | DAVID STEPANYAN |
| Permit Finaled | 9/3/2020 | JOHN JANSON |
| CofO Issued | 9/3/2020 | JOHN JANSON |
| Permit Finaled | 9/3/2020 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 2/28/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/28/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 3/17/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 3/31/2020 | DAVID MATSON |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/27/2020 | Partial Approval | DAVID STEPANYAN |
| Sewer | 4/27/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 4/27/2020 | Partial Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 5/6/2020 | Corrections Issued | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 5/8/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/2/2020 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 6/2/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Rough | 6/2/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 6/2/2020 | Corrections Issued | DAVID STEPANYAN |
| Insulation | 6/2/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 6/2/2020 | Approved | DAVID STEPANYAN |
| Rough-Elec/Plmb/HVAC | 6/2/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/8/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Rough | 6/8/2020 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 6/8/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/8/2020 | Partial Approval | DAVID STEPANYAN |
| Shower Pan | 6/8/2020 | Approved | DAVID STEPANYAN |
| Insulation | 6/11/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 6/11/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 6/15/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 8/24/2020 | Approved | DAVID STEPANYAN |
| Final | 8/24/2020 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 8/24/2020 | Approved | DAVID STEPANYAN |
| Green Building Final | 8/24/2020 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Service/Power Release | 8/24/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Smoke Detectors | 8/24/2020 | Corrections Issued | DAVID STEPANYAN |
| Final | 9/2/2020 | OK to Issue CofO | DAVID STEPANYAN |
| Green Building Final | 9/2/2020 | Approved | DAVID STEPANYAN |
| HVAC-Final | 9/2/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 9/2/2020 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2020 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 9/2/2020 | Approved | DAVID STEPANYAN |