23023 W SATICOY ST 91304

Certificate Information: 23023 W SATICOY ST 91304

Application / Permit
20014-20000-00087
Plan Check / Job No.
B20VN00380
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
6'9"X21'6" ADDITION & CONVERT 21'2"X21'6" GARAGE TO ACCESSORY DWELLING UNIT. ALL WORK PER WFPP
Permit Issued
Issued on 4/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2020 APPLICANT
Green Plans Picked Up 2/14/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 MARVEL DELACRUZ
Corrections Issued 2/23/2020 MARVEL DELACRUZ
Quality Review Completed 2/26/2020 GUANG MIN TUNG
Building Plans Picked Up 2/26/2020 APPLICANT
Applicant returned to address corrections 3/20/2020 MARVEL DELACRUZ
Plan Check Approved 4/9/2020 MARVEL DELACRUZ
Issued 4/22/2020 LADBS
CofO in Progress 9/2/2020 DAVID STEPANYAN
Permit Finaled 9/3/2020 JOHN JANSON
CofO Issued 9/3/2020 JOHN JANSON
Permit Finaled 9/3/2020 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/28/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/28/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 2/28/2020 ADRIAN CASTRO
Sewer availability Cleared 2/28/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 3/17/2020 GEORGE SUCHAND
Green Code Cleared 3/31/2020 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/27/2020 Partial Approval DAVID STEPANYAN
Sewer 4/27/2020 Approved DAVID STEPANYAN
Underground Mechanical 4/27/2020 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 5/6/2020 Corrections Issued DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 5/8/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 6/2/2020 Partial Approval DAVID STEPANYAN
ELECTRICAL-Rough 6/2/2020 Corrections Issued DAVID STEPANYAN
Green Building Rough 6/2/2020 Approved DAVID STEPANYAN
HVAC-Rough 6/2/2020 Corrections Issued DAVID STEPANYAN
Insulation 6/2/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 6/2/2020 Approved DAVID STEPANYAN
Rough-Elec/Plmb/HVAC 6/2/2020 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 6/8/2020 Approved DAVID STEPANYAN
ELECTRICAL-Rough 6/8/2020 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 6/8/2020 Approved DAVID STEPANYAN
HVAC-Rough 6/8/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 6/8/2020 Partial Approval DAVID STEPANYAN
Shower Pan 6/8/2020 Approved DAVID STEPANYAN
Insulation 6/11/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 6/11/2020 Approved DAVID STEPANYAN
Drywall Nailing 6/15/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 8/24/2020 Approved DAVID STEPANYAN
Final 8/24/2020 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 8/24/2020 Approved DAVID STEPANYAN
Green Building Final 8/24/2020 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 8/24/2020 SGSOV Not Ready DAVID STEPANYAN
Service/Power Release 8/24/2020 Not Ready for Inspection DAVID STEPANYAN
Smoke Detectors 8/24/2020 Corrections Issued DAVID STEPANYAN
Final 9/2/2020 OK to Issue CofO DAVID STEPANYAN
Green Building Final 9/2/2020 Approved DAVID STEPANYAN
HVAC-Final 9/2/2020 Approved DAVID STEPANYAN
PLUMBING-Final 9/2/2020 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 9/2/2020 SGSOV Approved DAVID STEPANYAN
Smoke Detectors 9/2/2020 Approved DAVID STEPANYAN