5853 N BURNET AVE 91411
Certificate Information: 5853 N BURNET AVE 91411
- Application / Permit
- 20014-20000-00080
- Plan Check / Job No.
- B20VN00366
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 3/11/2020
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 3/11/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2020 | APPLICANT |
| Green Plans Picked Up | 1/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | JOE VO |
| Corrections Issued | 2/3/2020 | JOE VO |
| Quality Review Completed | 2/5/2020 | KEN GILL |
| Building Plans Picked Up | 2/6/2020 | APPLICANT |
| Plan Check Approved | 3/9/2020 | JOE VO |
| Issued | 3/11/2020 | LADBS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/10/2020 | RIDWAN HARDY |
| Address approval | Cleared | 2/18/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/18/2020 | LEE GUILBEAUX |
| Green Code | Cleared | 2/28/2020 | AARON COSTA |
| ZI | Cleared | 3/2/2020 | RICHARD REASER |
| Low Impact Development | Cleared | 3/9/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 3/9/2020 | JEANIE LAM |
Contact Information
| Architect | Lee,, Kenneth David; Lic. No.: C10141 | 16501 ACADEMIA DRIVE ENCINO, CA 91436 |
| Contractor | Precision Construction Experts Inc; Lic. No.: 1026997-B | 16656 CALLE ARBOLADA PACIFIC PALISADES, CA 90272 |
| Engineer | Shakiban,, George; Lic. No.: C39908 | 23945 CALABASAS RD STE 101 CALABASAS, CA 91302 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/25/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 3/26/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/26/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| METHANE-Barrier | 3/26/2020 | Approved | MISAEL ESPARZA |
| METHANE-Subgrade | 3/26/2020 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/26/2020 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 3/27/2020 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/1/2020 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/1/2020 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/5/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2020 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 5/5/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| METHANE-Rough | 5/5/2020 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/13/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/13/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 5/13/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 5/13/2020 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 5/13/2020 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 5/13/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/14/2020 | Conditional Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 5/14/2020 | Approved | MISAEL ESPARZA |
| Sewer | 5/14/2020 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/27/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/3/2020 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 6/3/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/11/2020 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Rough | 6/11/2020 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/15/2020 | Corrections Issued | DANIEL DREW |
| Green Building Rough | 6/15/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 6/16/2020 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/18/2020 | Corrections Issued | MISAEL ESPARZA |
| Final | 6/18/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 6/18/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 6/18/2020 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/18/2020 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 6/18/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/10/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/10/2020 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 7/10/2020 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/10/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 7/14/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 7/16/2020 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 7/21/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 7/21/2020 | Approved | WILLIAM KUEHN |
| Drywall Nailing | 7/28/2020 | Approved | DANIEL ORRANTE |
| Drywall Nailing | 7/30/2020 | Approved | DANIEL ORRANTE |
| ELECTRICAL-Final | 11/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 11/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Gas Test | 11/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 11/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 11/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Final | 11/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 11/30/2020 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 11/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 1/26/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 1/26/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Gas Test | 1/26/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 1/26/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 1/26/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Final | 1/26/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Service/Power Release | 1/26/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Smoke Detectors | 1/26/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 4/9/2021 | Not Ready for Inspection | MARK JOHNSON |
| Final | 4/9/2021 | Not Ready for Inspection | MARK JOHNSON |
| Green Building Final | 4/9/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Final | 4/9/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Final | 4/9/2021 | Not Ready for Inspection | MARK JOHNSON |
| Smoke Detectors | 4/9/2021 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Final | 8/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 8/13/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 8/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Final | 8/13/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 8/13/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 8/13/2021 | Approved | JENNIFER RABUCHIN |
| Final | 3/24/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 3/24/2025 | Not Ready for Inspection | RYAN SALAZAR |