7126 N WILBUR AVE 91335
Certificate Information: 7126 N WILBUR AVE 91335
- Application / Permit
- 20014-20000-00074
- Plan Check / Job No.
- B20VN00335
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF 8' X 20'TO (E) 18' X 20' GARAGE AND CONVERT ENTIRE STRUCTURE TO ACCESSORY DWELLING UNIT ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/2/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/29/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2020 | APPLICANT |
| Green Plans Picked Up | 2/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 2/24/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 3/2/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/4/2020 | APPLICANT |
| Plan Check Approved | 8/14/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 9/2/2020 | APPLICANT |
| CofO in Progress | 11/17/2020 | VINCENT HANLEY |
| Permit Finaled | 12/29/2020 | DONALD SUNSERI |
| CofO Issued | 12/29/2020 | DONALD SUNSERI |
| Permit Finaled | 12/29/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Address approval | Cleared | 3/4/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/4/2020 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 5/28/2020 | RIDWAN HARDY |
| ZI | Cleared | 6/9/2020 | LAUREN PADICK |
| ZI | Cleared | 6/9/2020 | LAUREN PADICK |
| ZI | Cleared | 6/9/2020 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 6/16/2020 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/21/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 7/28/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/17/2020 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/1/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 10/1/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 10/1/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/7/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/7/2020 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 10/7/2020 | Approved | VINCENT HANLEY |
| Shower Pan | 10/7/2020 | Approved | VINCENT HANLEY |
| Insulation | 10/13/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/13/2020 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 10/13/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/15/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/15/2020 | Approved | VINCENT HANLEY |
| Shower Pan | 10/15/2020 | Approved | VINCENT HANLEY |
| Underground Mechanical | 10/15/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 11/12/2020 | Approved | VINCENT HANLEY |
| Final | 11/12/2020 | Corrections Issued | VINCENT HANLEY |
| Gas Test | 11/12/2020 | Approved | VINCENT HANLEY |
| Green Building Final | 11/12/2020 | Approved | VINCENT HANLEY |
| HVAC-Final | 11/12/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 11/12/2020 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 11/12/2020 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 11/12/2020 | Approved | VINCENT HANLEY |
| Final | 11/17/2020 | OK to Issue CofO | VINCENT HANLEY |