1041 S COCHRAN AVE 90019

Certificate Information: 1041 S COCHRAN AVE 90019

Application / Permit
20014-20000-00072
Plan Check / Job No.
B20VN00318
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 13'0"X17'5-1/2" TO & CONVERT (E) 20'3-7/8"X22'3-1/2" GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2020 APPLICANT
Green Plans Picked Up 2/12/2020 APPLICANT
Assigned to Plan Check Engineer 2/20/2020 MARVEL DELACRUZ
Corrections Issued 2/27/2020 MARVEL DELACRUZ
Quality Review Completed 2/27/2020 GUANG MIN TUNG
Building Plans Picked Up 2/28/2020 APPLICANT
Applicant returned to address corrections 4/16/2021 MARVEL DELACRUZ
Applicant returned to address corrections 5/7/2021 MARVEL DELACRUZ
Plan Check Approved 6/23/2021 MARVEL DELACRUZ
Issued 7/1/2021 APPLICANT
CofO in Progress 1/18/2022 ARTHUR SARGSYAN
CofO in Progress 1/18/2022 ARTHUR SARGSYAN
Permit Finaled 5/21/2022 DEROLD HAUFF
CofO Issued 5/21/2022 DEROLD HAUFF
Permit Finaled 5/21/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/19/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 2/22/2021 CECILIO NAVARRO
Sewer availability Cleared 2/22/2021 CECILIO NAVARRO
Green Code Cleared 2/24/2021 MICHAEL AYERS
Roof/Waste drainage to street Cleared 3/3/2021 CECILIO NAVARRO
HPOZ Cleared 4/20/2021 CHRISTINA PARK
Historic monument Cleared 4/20/2021 CHRISTINA PARK
ZI Cleared 4/20/2021 CHRISTINA PARK

Contact Information

Contractor Savin Construction; Lic. No.: 876774-B 1321 E ACACIA AVE APT A      GLENDALE, CA 91205
Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/20/2021 Corrections Issued JOSEPH MCGARRY
METHANE-Subgrade 7/20/2021 Not Ready for Inspection JOSEPH MCGARRY
Sewer 7/20/2021 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 7/28/2021 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Barrier 7/28/2021 Not Ready for Inspection JOSEPH MCGARRY
METHANE-Subgrade 7/28/2021 Not Ready for Inspection JOSEPH MCGARRY
Sewer 7/28/2021 Not Ready for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 8/4/2021 Not Ready for Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 8/9/2021 Approved ARTHUR SARGSYAN
METHANE-Barrier 8/9/2021 Approved ARTHUR SARGSYAN
METHANE-Subgrade 8/9/2021 Approved ARTHUR SARGSYAN
Sewer 9/13/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 9/22/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 9/22/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/22/2021 Approved CHRIS CHRISTENSEN
Sewer 9/22/2021 Approved CHRIS CHRISTENSEN
Wood Frame 9/22/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Wood Construction 9/24/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/24/2021 Partial Approval CHRIS CHRISTENSEN
Shower Pan 9/24/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/4/2021 Approved ARTHUR SARGSYAN
Insulation 10/6/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 10/15/2021 Approved ARTHUR SARGSYAN
Green Building Rough 10/15/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 11/9/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Final 11/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 12/8/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 12/8/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Final 12/8/2021 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Final 12/8/2021 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Rough 12/8/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 12/8/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/14/2022 Approved ARTHUR SARGSYAN
Final 1/14/2022 OK to Issue CofO ARTHUR SARGSYAN
Green Building Final 1/14/2022 Approved ARTHUR SARGSYAN
METHANE-Final 1/14/2022 Approved ARTHUR SARGSYAN
METHANE-Rough 1/14/2022 Approved ARTHUR SARGSYAN
Service/Power Release 3/18/2022 Approved ARTHUR SARGSYAN