15111 W SEPTO ST 91345
Certificate Information: 15111 W SEPTO ST 91345
- Application / Permit
- 20014-20000-00070
- Plan Check / Job No.
- B20VN00309
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel to the 1-story single-family dwelling with attached garage
- Permit Issued
- Issued on 2/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2020 | APPLICANT |
| Green Plans Picked Up | 1/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | ANGELICA DAVE |
| Corrections Issued | 1/27/2020 | ANGELICA DAVE |
| Quality Review Completed | 1/28/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/31/2020 | APPLICANT |
| Plan Check Approved | 2/24/2020 | ANGELICA MARTINEZ |
| Issued | 2/24/2020 | LADBS |
| CofO in Progress | 12/5/2020 | JENNIFER RABUCHIN |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
| CofO Issued | 12/26/2020 | MICHAEL SMITH |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 2/7/2020 | JOHN TRIANTAFYLLOS |
| Green Code | Cleared | 2/12/2020 | AARON COSTA |
| Low Impact Development | Cleared | 2/24/2020 | ANDRES COVARRUBIAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/4/2020 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 3/20/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/3/2020 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 4/3/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/15/2020 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 4/15/2020 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/20/2020 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/20/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 5/20/2020 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 5/20/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/20/2020 | Approved | JENNIFER RABUCHIN |
| Sewer | 5/20/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/26/2020 | Approved | TROY SANDERS |
| HVAC-Rough | 5/26/2020 | Approved | TROY SANDERS |
| Insulation | 6/19/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/19/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 6/25/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/25/2020 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/10/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 7/24/2020 | Corrections Issued | MICHAEL TEMPLE |
| Special/Order Compliance | 7/24/2020 | Corrections Issued | MICHAEL TEMPLE |
| Shower Pan | 8/19/2020 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 11/25/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 11/25/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 11/25/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/25/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 11/25/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 11/25/2020 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 11/25/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 11/25/2020 | Approved | JENNIFER RABUCHIN |
| Final | 11/30/2020 | OK to Issue CofO | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/7/2020 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 12/7/2020 | Approved | JENNIFER RABUCHIN |