8224 N MCLAREN AVE 91304

Certificate Information: 8224 N MCLAREN AVE 91304

Application / Permit
20014-20000-00053
Plan Check / Job No.
B20VN00233
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
21'-5" X 15'-0" ADDITION TO AND CONVERT (E) DETACHED REC ROOM / GARAGE TO ACCESSORY DWELLING UNIT. COMPLY WITH DEPARTMENT ORDER effective date 11/11/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 3/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2020 APPLICANT
Green Plans Picked Up 2/12/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 JEROME MAGAT PALMA
Corrections Issued 2/13/2020 JEROME MAGAT PALMA
Building Plans Picked Up 2/19/2020 APPLICANT
Plan Check Approved 3/4/2020 JEROME MAGAT PALMA
Issued 3/4/2020 LADBS
CofO in Progress 10/13/2020 HAGOP BADOSSIAN
CofO Issued 11/10/2020 DAVID JAMES
Permit Finaled 11/10/2020 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 2/20/2020 JOHN LIN
Construction near power lines Cleared 2/21/2020 TORI CHEN
Eng Process Fee Ord 176,300 Cleared 2/25/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 2/25/2020 GABRIEL ROBLES
Sewer availability Cleared 2/25/2020 GABRIEL ROBLES
Green Code Cleared 3/4/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/12/2020 Corrections Issued HAGOP BADOSSIAN
Deputy Drilled-In Anchors 5/21/2020 Conditional Approval HAGOP BADOSSIAN
Excavation/Setback/Form/Re-Bar 5/27/2020 Partial Approval HAGOP BADOSSIAN
Excavation/Setback/Form/Re-Bar 6/2/2020 Approved HAGOP BADOSSIAN
Interior/Exterior Lathing 6/9/2020 Partial Approval HAGOP BADOSSIAN
PLUMBING-Rough 6/9/2020 Partial Approval HAGOP BADOSSIAN
ELECTRICAL-Rough 6/22/2020 Not Ready for Inspection HAGOP BADOSSIAN
HVAC-Rough 6/22/2020 Not Ready for Inspection HAGOP BADOSSIAN
Interior/Exterior Lathing 6/22/2020 Not Ready for Inspection HAGOP BADOSSIAN
PLUMBING-Rough 6/22/2020 Partial Approval HAGOP BADOSSIAN
ELECTRICAL-Rough 6/24/2020 Approved HAGOP BADOSSIAN
PLUMBING-Rough 6/24/2020 Approved HAGOP BADOSSIAN
HVAC-Rough 6/26/2020 Approved HAGOP BADOSSIAN
Interior/Exterior Lathing 6/26/2020 Partial Approval HAGOP BADOSSIAN
Shower Pan 6/26/2020 Approved HAGOP BADOSSIAN
Wood Frame 6/26/2020 Approved HAGOP BADOSSIAN
Insulation 6/29/2020 Approved HAGOP BADOSSIAN
Interior/Exterior Lathing 6/29/2020 Approved HAGOP BADOSSIAN
Drywall Nailing 7/6/2020 Approved HAGOP BADOSSIAN
BUILDING-Rough-Frame 10/5/2020 Approved HAGOP BADOSSIAN
Final 10/5/2020 Corrections Issued HAGOP BADOSSIAN
Footing/Foundation/Slab 10/5/2020 Approved HAGOP BADOSSIAN
Green Building Final 10/5/2020 Approved HAGOP BADOSSIAN
Green Building Rough 10/5/2020 Approved HAGOP BADOSSIAN
SGSOV-Seismic Gas S/O Valve 10/5/2020 SGSOV Approved HAGOP BADOSSIAN
Smoke Detectors 10/5/2020 Approved HAGOP BADOSSIAN
Final 10/6/2020 Partial Approval HAGOP BADOSSIAN
Final 10/8/2020 Conditional Approval HAGOP BADOSSIAN