10045 N AMBOY AVE 91331
Certificate Information: 10045 N AMBOY AVE 91331
- Application / Permit
- 20014-20000-00036
- Plan Check / Job No.
- B20VN00159
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 20' X 18' (E) 2-CAR GARAGE TO ADU AND ADD 14' X 14' TO ADU. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 4/28/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/26/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 2/13/2020 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 3/4/2020 | APPLICANT |
| Green Plans Picked Up | 3/4/2020 | APPLICANT |
| Plan Check Approved | 4/17/2020 | GURUNATH NESARAJAH |
| Issued | 4/28/2020 | LADBS |
| CofO in Progress | 10/30/2020 | MICHEL ABAJAN |
| CofO Issued | 12/26/2020 | MICHAEL SMITH |
| Permit Finaled | 12/26/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/11/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/11/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 3/18/2020 | AARON COSTA |
| Clean Up Green Up | Cleared | 3/24/2020 | TERRI OSBORNE |
Contact Information
| No Data Available. |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/15/2020 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 6/15/2020 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/1/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 7/1/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 7/1/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/24/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/24/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/24/2020 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 7/24/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/24/2020 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 7/24/2020 | Partial Approval | MICHEL ABAJAN |
| Insulation | 7/29/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/29/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 7/29/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Drywall Nailing | 7/31/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 7/31/2020 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 7/31/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/4/2020 | Approved | MICHEL ABAJAN |
| Sewer | 8/4/2020 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/8/2020 | Approved | MICHEL ABAJAN |
| Final | 10/8/2020 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/8/2020 | Approved | MICHEL ABAJAN |
| HVAC-Final | 10/8/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/8/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2020 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 10/8/2020 | Approved | MICHEL ABAJAN |
| Final | 10/27/2020 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2020 | SGSOV Approved | MICHEL ABAJAN |
| Final | 10/30/2020 | OK to Issue CofO | MICHEL ABAJAN |