10045 N AMBOY AVE 91331

Certificate Information: 10045 N AMBOY AVE 91331

Application / Permit
20014-20000-00036
Plan Check / Job No.
B20VN00159
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20' X 18' (E) 2-CAR GARAGE TO ADU AND ADD 14' X 14' TO ADU. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 4/28/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/26/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 GURUNATH NESARAJAH
Corrections Issued 2/13/2020 GURUNATH NESARAJAH
Building Plans Picked Up 3/4/2020 APPLICANT
Green Plans Picked Up 3/4/2020 APPLICANT
Plan Check Approved 4/17/2020 GURUNATH NESARAJAH
Issued 4/28/2020 LADBS
CofO in Progress 10/30/2020 MICHEL ABAJAN
CofO Issued 12/26/2020 MICHAEL SMITH
Permit Finaled 12/26/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/11/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 3/11/2020 GABRIEL ROBLES
Sewer availability Cleared 3/11/2020 GABRIEL ROBLES
Green Code Cleared 3/18/2020 AARON COSTA
Clean Up Green Up Cleared 3/24/2020 TERRI OSBORNE

Contact Information

No Data Available.

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/15/2020 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 6/15/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 7/1/2020 Approved MICHEL ABAJAN
METHANE-Barrier 7/1/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 7/1/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/24/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/24/2020 Approved MICHEL ABAJAN
Green Building Rough 7/24/2020 Approved MICHEL ABAJAN
METHANE-Rough 7/24/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 7/24/2020 Approved MICHEL ABAJAN
Underground Mechanical 7/24/2020 Partial Approval MICHEL ABAJAN
Insulation 7/29/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/29/2020 Corrections Issued JENNIFER RABUCHIN
Shower Pan 7/29/2020 Not Ready for Inspection JENNIFER RABUCHIN
Drywall Nailing 7/31/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/31/2020 Partial Approval JENNIFER RABUCHIN
Shower Pan 7/31/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/4/2020 Approved MICHEL ABAJAN
Sewer 8/4/2020 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 10/8/2020 Approved MICHEL ABAJAN
Final 10/8/2020 Corrections Issued MICHEL ABAJAN
Green Building Final 10/8/2020 Approved MICHEL ABAJAN
HVAC-Final 10/8/2020 Approved MICHEL ABAJAN
PLUMBING-Final 10/8/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/8/2020 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 10/8/2020 Approved MICHEL ABAJAN
Final 10/27/2020 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/27/2020 SGSOV Approved MICHEL ABAJAN
Final 10/30/2020 OK to Issue CofO MICHEL ABAJAN