13077 W GOLETA ST 91331
Certificate Information: 13077 W GOLETA ST 91331
- Application / Permit
- 20014-20000-00029
- Plan Check / Job No.
- B20VN00120
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 16'10"x17'5" TO ADD A BEDROOM AND A FULL BATHROOM, AND INTERIOR ALTERATION TO INCLUDE REMODEL BATHROOM, RELOCATE KITCHEN. DWELLING TO HAVE THREE BEDROOMS, TWO FULL BATHROOMS, KITCHEN/DINING ROOM/LIVING ROOM.
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2020 | LUIS RINCON |
| Corrections Issued | 1/6/2020 | LUIS RINCON |
| Plan Check Approved | 1/8/2020 | LUIS RINCON |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 8/14/2023 | MICHEL ABAJAN |
| Permit Finaled | 9/20/2023 | RUBEN SALAS |
| CofO Issued | 9/20/2023 | RUBEN SALAS |
| Permit Finaled | 9/20/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2020 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 1/8/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/8/2020 | MARKOS PEREZ-BRAN |
| Office of Finance Referral | Cleared | 1/13/2020 | TRANG MCCONNAUGHY |
Contact Information
| Contractor | J M A General Contractor; Lic. No.: 893018-B | 5817 MCDONIE AVENUE WOODLAND HILLS, CA 91367 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2020 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Barrier | 2/3/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Subgrade | 2/3/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 2/3/2020 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/5/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 3/5/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 3/5/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/6/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2020 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 4/6/2020 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/28/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 4/28/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 4/28/2020 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 4/28/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/28/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/6/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/6/2020 | Approved | MICHEL ABAJAN |
| Insulation | 5/13/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/13/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/28/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/13/2023 | Approved | MICHEL ABAJAN |
| Final | 7/13/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 7/13/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/13/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 7/13/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 7/13/2023 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 8/9/2023 | Conditional Approval | ROBERT GOLD |
| Final | 8/14/2023 | OK to Issue CofO | MICHEL ABAJAN |