10141-10143 N FARRALONE AVE 91311

Certificate Information: 10141-10143 N FARRALONE AVE 91311

Application / Permit
20014-20000-00009
Plan Check / Job No.
B20VN00027
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SINGLE FAMILY DWELLING: CONVERT (E) 25'-9 X 20' GARAGE TO TWO ADDITIONAL BEDROOMS, ADD (N) IRREGULAR SHAPED 32'-6" X 32'-3" REC-ROOM W/ ATTACHED STORAGE AND ADD (N) IRREGULAR SHAPED 32'3" X 23' SECOND STORY ACCESSORY DWELLING UNIT ABOVE REC-ROOM, (N) 34' X 10' ATTACHED CARPORT ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/14/2020
Issuing Office
Current Status
CofO Issued on 9/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 2/19/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 2/25/2020 OMID HEDAYAT
Building Plans Picked Up 2/25/2020 APPLICANT
Green Plans Picked Up 5/1/2020 APPLICANT
Plan Check Approved 8/14/2020 SEWADA ZADOORAN MILAGARDI
Issued 8/14/2020 APPLICANT
CofO in Progress 7/21/2022 DAVID SCANTLIN
Permit Finaled 9/29/2022 JOHN JANSON
CofO Issued 9/29/2022 JOHN JANSON
Permit Finaled 9/29/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/25/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/25/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 2/25/2020 BARTON HOLMES
Roof/Waste drainage to street Cleared 2/25/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/25/2020 JOHN TRIANTAFYLLOS
Certificate of Compliance Cleared 3/2/2020 DANG NGUYEN
Miscellaneous Cleared 3/2/2020 DANG NGUYEN
Green Code Cleared 4/2/2020 KHEDER ALRAZAA
Low Impact Development Cleared 6/30/2020 ROBIN YAMADA
GPI Written Notices Cleared 8/4/2020 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Ko General Construction; Lic. No.: 1046527-B 12940 MACNEIL      SYLMAR, CA 91342
Engineer Schulz,, Les Eric; Lic. No.: S2570 346 N LIMA      SIERRA MADRE, CA 91024

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/19/2020 Partial Approval DAVID STEPANYAN
Sewer 10/19/2020 Approved DAVID STEPANYAN
Underground Mechanical 10/19/2020 Partial Approval DAVID STEPANYAN
Gas Test 10/27/2020 Partial Approval DAVID STEPANYAN
Underground Mechanical 10/27/2020 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 11/9/2020 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2020 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Not Ready for Inspection DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 1/25/2021 Approved DAVID STEPANYAN
Underground Mechanical 2/25/2021 Partial Approval DAVID STEPANYAN
Gas Test 3/8/2021 Partial Approval DAVID STEPANYAN
HVAC-Rough 3/8/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 3/8/2021 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 3/17/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 3/17/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 3/17/2021 Corrections Issued DAVID STEPANYAN
HVAC-Rough 3/17/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 4/19/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 4/19/2021 Partial Approval DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 5/13/2021 Partial Approval DAVID STEPANYAN
Deputy Reinf. Concrete 5/17/2021 Conditional Approval DAVID STEPANYAN
BUILDING-Rough-Frame 6/10/2021 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 6/10/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Rough 6/10/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 7/1/2021 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 7/1/2021 Approved DAVID SCANTLIN
Green Building Rough 7/1/2021 Not Ready for Inspection DAVID SCANTLIN
Deputy Wood Construction 7/2/2021 Partial Approval SHAVONNE ESPINOZA
BUILDING-Rough-Frame 7/7/2021 Not Ready for Inspection DAVID STEPANYAN
Green Building Rough 7/7/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 7/7/2021 Partial Approval DAVID STEPANYAN
Insulation 8/4/2021 Corrections Issued JENNIFER RABUCHIN
Insulation 8/10/2021 Not Ready for Inspection ASHLEY THOMPSON
Insulation 8/13/2021 Corrections Issued STEPHANIE SWANSON
Insulation 8/19/2021 Not Ready for Inspection DAVID SCANTLIN
Insulation 8/24/2021 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 8/30/2021 Corrections Issued STEPHANIE SWANSON
Insulation 8/30/2021 Approved STEPHANIE SWANSON
Drywall Nailing 9/8/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 9/20/2021 Partial Approval DAVID STEPANYAN
Footing/Foundation/Slab 12/14/2021 Approved DAVID STEPANYAN
Structural Steel Frame 12/14/2021 Approved DAVID STEPANYAN
Wood Frame 12/14/2021 Partial Approval DAVID STEPANYAN
BUILDING-Rough-Frame 4/19/2022 Corrections Issued CHRIS CHRISTENSEN
Final 4/19/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 4/19/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/19/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 4/19/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/16/2022 Approved TROY SANDERS
Final 5/16/2022 Not Ready for Inspection TROY SANDERS
Green Building Final 5/16/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/16/2022 SGSOV Approved TROY SANDERS
ELECTRICAL-Final 7/20/2022 Approved DAVID SCANTLIN
Final 7/20/2022 OK to Issue CofO DAVID SCANTLIN
HVAC-Final 7/20/2022 Approved DAVID SCANTLIN
PLUMBING-Final 7/20/2022 Approved DAVID SCANTLIN