841-845 E VENICE BLVD 90291
Certificate Information: 841-845 E VENICE BLVD 90291
- Application / Permit
- 20014-10006-02188
- Plan Check / Job No.
- B23LA06175
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (2) Duplex
- Work Description
- *ePlan* Supplemental permit to 20014-10000-02188 Change work description from alter/repair & addition of (E) SFD and convert to Duplex (2nd floor) and Supportive Services (offices) (1st Floor and part of affordability project per LAMC 14.13 (Qualified Permanent Supportive Housing Project) to New Construction of 2-story Duplex (2nd floor) and supportive services / offices to comply with the 2023 LABC. (see comments)
- Permit Issued
- Issued on 12/12/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2023 | MINA HABIB |
| Corrections Issued | 5/3/2023 | MINA HABIB |
| Quality Review Completed | 5/5/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 8/14/2023 | MINA HABIB |
| Applicant returned to address corrections | 8/16/2023 | MINA HABIB |
| Applicant returned to address corrections | 8/17/2023 | MINA HABIB |
| Applicant returned to address corrections | 8/21/2023 | MINA HABIB |
| Applicant returned to address corrections | 11/7/2023 | MINA HABIB |
| Applicant returned to address corrections | 11/15/2023 | MINA HABIB |
| Applicant returned to address corrections | 11/16/2023 | MINA HABIB |
| Applicant returned to address corrections | 12/4/2023 | MINA HABIB |
| Applicant returned to address corrections | 12/5/2023 | MINA HABIB |
| Plan Check Approved | 12/7/2023 | MINA HABIB |
| Issued | 12/12/2023 | APPLICANT |
| Permit Finaled | 5/19/2025 | FARHAD DADBIN |
Permit Application Clearance Information
| Green Code | Cleared | 4/13/2023 | Rodolfo Arias |
| Coastal Zone | Cleared | 5/8/2023 | LOUIS ORTEGA |
| Coastal Zone | Cleared | 5/8/2023 | LOUIS ORTEGA |
| Frnt yard landscape/Water mgmt | Cleared | 5/8/2023 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 5/8/2023 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 5/8/2023 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 5/8/2023 | LOUIS ORTEGA |
| Opn space landscape/Water mgmt | Cleared | 5/8/2023 | LOUIS ORTEGA |
| Permanent Supportive Housing | Cleared | 5/8/2023 | LOUIS ORTEGA |
| Specific Plan | Cleared | 5/8/2023 | LOUIS ORTEGA |
| Low Impact Development (LID) | Cleared | 5/11/2023 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/16/2023 | JASON NG |
| Specific Plan | Cleared | 5/16/2023 | ALESSANDRO MERCURI |
| Density Bonus 14.00.A.13 | Cleared | 5/17/2023 | MARITES CUNANAN |
| SB8 RUD | Cleared | 5/17/2023 | MARITES CUNANAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2023 | JASON NG |
| Sewer availability | Cleared | 5/31/2023 | JASON NG |
| Highway dedication | Cleared | 6/1/2023 | AHMED AMARRAGY |
| Hydrant and Access approval | Cleared | 6/13/2023 | JOHN CONNEALLY |
| DAS Clearance | Cleared | 6/23/2023 | Rodolfo Arias |
| Work Adjacent to Public Way | Cleared | 7/11/2023 | LIAM ODONOVAN |
Contact Information
| Architect | Daly,, Kevin Michael; Lic. No.: C19005 | 3617 W EXPOSITION BLVD LOS ANGELES, CA 90016 |
| Contractor | Mid Construction Group; Lic. No.: 1030925-B | 5850 W 3RD STREET #160 LOS ANGELES, CA 90036 |
| Engineer | Varela,, Benjamin; Lic. No.: S5714 | 6007 WASHINGTON BLVD CULVER CITY, CA 90232 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/26/2023 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 1/3/2024 | Corrections Issued | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 1/5/2024 | Corrections Issued | FARHAD DADBIN |
| Pre-Inspection | 6/17/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Partial Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 7/25/2024 | Conditional Approval | FARHAD DADBIN |
| Green Building Rough | 8/7/2024 | Approved | FARHAD DADBIN |
| Verify Sprinkler Sign Off | 8/7/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 8/7/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 8/9/2024 | Not Ready for Inspection | NICK LAROCCA |
| Verify Sprinkler Sign Off | 8/14/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 8/14/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Verify Sprinkler Sign Off | 8/16/2024 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 8/16/2024 | Partial Approval | FARHAD DADBIN |
| Deputy Wood Construction | 8/19/2024 | Conditional Approval | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2024 | Partial Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 9/5/2024 | Conditional Approval | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 9/18/2024 | Conditional Approval | FARHAD DADBIN |
| Deputy Wood Construction | 9/20/2024 | Conditional Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Partial Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 9/23/2024 | Partial Approval | FARHAD DADBIN |
| Deputy Wood Construction | 10/22/2024 | Conditional Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Partial Approval | FARHAD DADBIN |
| Deputy Wood Construction | 10/30/2024 | Conditional Approval | FARHAD DADBIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Partial Approval | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 11/6/2024 | Corrections Issued | RICARDO ROBLES |
| Deputy Steel/Welding | 11/12/2024 | Approved | FARHAD DADBIN |
| Verify Sprinkler Sign Off | 1/28/2025 | Approved | FARHAD DADBIN |
| Wood Frame | 1/28/2025 | Approved | FARHAD DADBIN |
| Insulation | 1/30/2025 | Approved | FARHAD DADBIN |
| Drywall Nailing | 2/4/2025 | Approved | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 3/18/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 3/19/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 3/19/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 3/19/2025 | Approved | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 3/20/2025 | Partial Approval | FARHAD DADBIN |
| Deputy Reinf. Concrete | 3/24/2025 | Conditional Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 4/1/2025 | Partial Approval | FARHAD DADBIN |
| Excavation/Setback/Form/Re-Bar | 4/18/2025 | Partial Approval | FARHAD DADBIN |
| Final | 4/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Footing/Foundation/Slab | 4/28/2025 | Approved | FARHAD DADBIN |
| Final | 5/19/2025 | Permit Finaled | FARHAD DADBIN |