2130 W 80TH ST 90047
Certificate Information: 2130 W 80TH ST 90047
- Application / Permit
- 20014-10003-01213
- Plan Check / Job No.
- B24LA33750
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- supplemental permit to 20014-10000-01213 to revise location of ADU and revise from conversion to new construction R3 occupancy
- Permit Issued
- Issued on 12/2/2024
- Issuing Office
- Metro
- Current Status
- Issued on 12/2/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2024 | KELVIN CHUONG |
| Plan Check Approved | 12/2/2024 | KELVIN CHUONG |
| Issued | 12/2/2024 | APPLICANT |
| Building Plans Picked Up | 12/2/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 184 S ALTADENA DRIVE PASADENA, CA 91107 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Service/Power Release | 6/8/2026 |
| ELECTRICAL-Final | 6/8/2026 |
| Final | 6/8/2026 |
| PLUMBING-Final | 6/8/2026 |
| HVAC-Final | 6/8/2026 |
Inspection Request History
| PLUMBING-Rough | 12/9/2024 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 12/20/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/20/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2025 | Partial Approval | RONNIE MINDANAO |
| ELECTRICAL-Rough | 1/24/2025 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 1/24/2025 | Corrections Issued | MICHAEL LEWIS |
| Wood Frame | 1/24/2025 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 1/28/2025 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 1/28/2025 | Approved | MICHAEL LEWIS |
| Green Building Rough | 1/28/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 1/28/2025 | Partial Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 1/28/2025 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 1/28/2025 | Approved | MICHAEL LEWIS |
| Insulation | 1/30/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 1/31/2025 | Partial Approval | ANTHONY RAMOS |
| Insulation | 1/31/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 2/4/2025 | Corrections Issued | ANTHONY RAMOS |
| Interior/Exterior Lathing | 2/4/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 2/10/2025 | Approved | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 3/26/2025 | Approved | MICHAEL LEWIS |
| Final | 3/26/2025 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 3/26/2025 | Approved | MICHAEL LEWIS |
| Service/Power Release | 3/26/2025 | Corrections Issued | MICHAEL LEWIS |
| Final | 4/11/2025 | Not Ready for Inspection | JOSE MACIAS |
| Service/Power Release | 4/11/2025 | Not Ready for Inspection | JOSE MACIAS |