3253 N DOS PALOS DR 90068

Certificate Information: 3253 N DOS PALOS DR 90068

Application / Permit
20014-10002-04288
Plan Check / Job No.
B22LA14506
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Supplemental Permit to 20014-10000-04288. 7'-4"x13' addtion at rear of existing garge and revise primary bed room layout.
Permit Issued
Issued on 10/2/2022
Issuing Office
Current Status
Permit Finaled on 5/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 AUNG SOE
Corrections Issued 8/22/2022 AUNG SOE
Quality Review Completed 9/3/2022 PRANITA SHAH
Applicant returned to address corrections 9/21/2022 AUNG SOE
Plan Check Approved 9/28/2022 AUNG SOE
Issued 10/2/2022 APPLICANT
Permit Finaled 5/9/2023 BRIAN SULLIVAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/22/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 9/22/2022 DAGOVERTO GUERRERO
Specific Plan Cleared 9/26/2022 OLGA AYALA

Contact Information

Architect Beauter,, William L; Lic. No.: NA29188       ,
Contractor Eazy Adu; Lic. No.: 1057881-B       ,
Contractor Greencast Construction Inc; Lic. No.: 1057881-B       ,

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/4/2022 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 10/6/2022 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 11/14/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Rough 11/14/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Rough-Elec/Plmb/HVAC 11/14/2022 Corrections Issued ALIZAH MAYAGOITIA
Insulation 11/17/2022 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 11/17/2022 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 11/23/2022 Corrections Issued BRIAN SULLIVAN
Green Building Rough 11/23/2022 Approved BRIAN SULLIVAN
HVAC-Rough 11/23/2022 Approved BRIAN SULLIVAN
Insulation 11/23/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 11/23/2022 Partial Approval BRIAN SULLIVAN
MERV13>=Rough 11/23/2022 Approved BRIAN SULLIVAN
Drywall Nailing 12/6/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 12/12/2022 Approved JOAQUIN GREENOUGH
Shower Pan 12/12/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 5/9/2023 Approved BRIAN SULLIVAN
Final 5/9/2023 Permit Finaled BRIAN SULLIVAN
Footing/Foundation/Slab 5/9/2023 Approved BRIAN SULLIVAN
Green Building Final 5/9/2023 Approved BRIAN SULLIVAN
MERV13>=Final 5/9/2023 Approved BRIAN SULLIVAN
Smoke Detectors 5/9/2023 Approved BRIAN SULLIVAN